Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UEAP/PWD/C2-B Agreement signed
Project: UEAP-RB Package No.: 1003 Package Name: UEAP/PWD/C2-B Sanction Cost: 150.00  lakhs
District: Almora Block: Sult Constituency: Ranikhet Circle:
DEA: DEA UEAP Almora DSC: TPF Getinsa Eurostudios S.L. in Association with V DSC Scope: Design & Supervision No.of Sub project : 1
Subproject in this package
1  5803   Ranikhet-Mohan (26.000 KM.) (completed)
Procurement:
Package No.: 1003        Package Name: UEAP/PWD/C2-B        Tender Date: 05-04-2014        Current Status: Agreement signed        Achieved on Date: 26-11-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C2-B        Contractor Name: Dwarika Projects Limited       
Start Date: 17-12-2014        Intended Completion Date: 05-08-2017        Original End Date:  16-03-2016
Total Bond Cost: 15877150.75 (158.77 lakhs)        Variation Cost: 622849.06 (6.23 lakhs)     Hence Total Bond Cost is   16499999.81 (165 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 285804 for 36 days        LD Analysis for Milestone2: calculated LD is Rs 1079704 for 136 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence5.00 KM4.305.00 KM5.00 KM2.614.30
2.R/Wall, B/ Wall Type Protection works220.00 m43.09220.00 m220.00 m26.1243.09
3.GSB/RBI/G-10.05 KM0.360.05 KM0.05 KM0.220.36
4.G-20.23 KM3.990.23 KM0.23 KM2.423.99
5.G-30.23 KM5.370.23 KM0.23 KM3.255.37
6.BM i/c Prime Coat, Tack Coat0.12 KM2.700.12 KM0.12 KM1.642.70
7.SDBC i/c Tackcoat0.27 KM45.580.27 KM0.27 KM27.6245.58
8.Cause Way2.00 No8.222.00 No2.00 No4.988.22
9.longitudinal Drain14852.00 m48.724850.00 m4850.00 m29.5348.72
10.Other Allied Works & Finishing Work 1.00 Job2.671.00 Job1.00 Job1.622.67
Total Amount: 165 100   165
Remarks: Work Completed.       Work Program Made On: 05-04-2017       Updation of work program on: 20-09-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.31-March-20157.34  lakhs
2.23-June-201524.04  lakhs
3.25-July-201539.36  lakhs
4.29-February-20168.56  lakhs
5.17-December-201653.25  lakhs
6.25-April-201731.85  lakhs
7.29-September-20170.60  lakhs
Total 165  lakhs
% Payment 100 %
Advance Amount:  15.88  lakhs        Recovered Amount:  15.88  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 190     No. of Test Done : 192      No. of Test Passed : 138      No. of Test Failed : 0      No. of Test Result Awaited : 50   Test report of this package
Number of Pics Available on Web Repository: 28
Number of Notice(s) issued: 84

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.29-08-20163.700KC Drain work is in progressGaurav BishtJEUEAP R&B Almora See Pic
2.29-08-2016Ch 3.50 near Power houseKC Drain work is in progressGaurav BishtJEUEAP R&B Almora See Pic
3.28-08-2016Ch 0.025KC Drain work is in progressGaurav BishtJEUEAP R&B Almora See Pic
4.28-08-2016Ch 5.200 starting of Tarikhet marketKC Drain work is in progressGaurav BishtJEUEAP R&B Almora See Pic
5.20-05-2016Ch 12.500PCC for KC drainChetan BhattJEUEAP R&B Almora See Pic
6.13-07-2015Ch.65.300Causeway DamageA S BishtEEDEA ADB Almora See Pic
7.13-07-2015Ch.60.600LandslideA S BishtEEDEA ADB Almora See Pic
8.13-07-2015Ch. 22.200LandslideA S BishtEEDEA ADB Almora See Pic
9.23-06-2015KM 57Patch work is in progressGaurav BishtJEUEAP R&B Almora See Pic
10.23-06-2015At Plant near Soni MarketSDBC For patch WorkGaurav BishtJEUEAP R&B Almora See Pic
11.23-06-2015Km13 (Soni Daat)Patch Work is in ProgressGaurav BishtJEUEAP R&B Almora See Pic
12.23-06-2015Km 26 Near Inspection House PWDPatch Work is in ProgressGaurav BishtJEUEAP R&B Almora See Pic
13.23-06-2015Km 26 Near Petrol Pump BhatrojkhanPatch Work is in ProgressGaurav BishtJEUEAP R&B Almora See Pic
14.23-06-2015Km 26 near Bhatrojkhan Filling stationPatch work is in progressGaurav BishtJEUEAP R&B Almora See Pic
15.18-05-2015Ch.63.800Patch repair workA S BishtEEDEA ADB Almora See Pic
16.18-05-2015Ch.62.400R/Wall with toe wall & scupperA S BishtEEDEA ADB Almora See Pic
17.18-05-2015Ch.57.800R/Wall in 1:5A S BishtEEDEA ADB Almora See Pic
18.28-03-2015Ch 0000Forward FriDwarika cons ` ` See Pic
19.28-03-2015Ch 0000For billingRoad-5803 ` ` See Pic
20.23-03-2015Ch.57.500R/wall CompletedGaurav BishtJEUEAP R&B Almora See Pic