UEAP/PWD/C1
Agreement signed
|
Project: |
UEAP-RB |
Package No.: |
1001 |
Package Name: |
UEAP/PWD/C1 |
Sanction Cost: |
710.00 lakhs |
District: |
Nainital |
Block: |
Kotabagh |
Constituency: |
Kaladhungi |
Circle: |
|
DEA: |
DEA UEAP Nainital |
DSC: |
CCEE Group India Pvt.Ltd |
DSC Scope: |
Design & Supervision |
No.of Sub project : |
2 |
Subproject in this package |
1 5901 Kaladhungi- Kotabagh-Belpadav Road (7.000 KM.) (completed) | 2 5902 Nainital-Kaladhungi- Bajpur Doraha Road (21.500 KM.) (completed) |
|
Procurement: |
Package No.: 1001
Package Name: UEAP/PWD/C1
Tender Date: 13-01-2014
Current Status: Agreement signed
Achieved on Date: 21-04-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C1
Contractor Name: Woodhill Infrastructure Ltd
|
Start Date: 16-06-2014
Intended Completion Date: 18-01-2016
Original End Date: 18-09-2015
|
Total Bond Cost: 58834744.2 (588.35 lakhs)
Variation Cost: 8740028.90 (87.4 lakhs) Hence Total Bond Cost is 67574773.1 (675.75 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 1000178 for 34 days
LD Analysis for Milestone2: calculated LD is Rs 1706186 for 58 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | BM i/c Prime Coat, Tack Coat | 1.86 KM | 38.71 | 1.37 KM | 1.37 KM | 8.4 | 38.71 | 2. | SDBC i/c Tackcoat | 21.05 KM | 296.65 | 21.55 KM | 21.55 KM | 64.76 | 296.65 | 3. | Culverts/Scupper | 5.00 No | 11.83 | 6.00 No | 6.00 No | 2.61 | 11.83 | 4. | Road Furniture | 156.00 No | 33.11 | 156.00 No | 156.00 No | 7.98 | 33.11 | 5. | Hill side Cutting & Slip clearence | 0.34 KM | 0.97 | 0.34 KM | 0.34 KM | 0.24 | 0.97 | 6. | R/Wall, B/ Wall Type Protection works | 910.00 m | 56.89 | 2773.00 m | 2773.00 m | 13.85 | 56.89 | 7. | Cause Way | 4.00 No | 7.52 | 4.00 No | 4.00 No | 1.83 | 7.52 | 8. | longitudinal Drain | 15113.00 m | 1.36 | 15580.00 m | 15580.00 m | 0.33 | 1.36 |
Total Amount: |
447.04 |
|
100 |
447.04 |
|
Remarks:
No Remarks
Work Program Made On:
17-04-2015
Updation of work program on:
25-05-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 27-April-2015 | 196.00 lakhs |
2. | 27-June-2015 | 120.70 lakhs |
3. | 30-October-2015 | 138.27 lakhs |
4. | 21-March-2016 | 135.20 lakhs |
5. | 15-June-2017 | 60.86 lakhs |
Total |
651.03 lakhs |
% Payment |
96.34 % |
|
Advance Amount: 58.00 lakhs
Recovered Amount: 58.00 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 34 |
Number of Notice(s) issued: 73 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 29-11-2016 | Chainage 3+008 | Checking of core by CE Hld Er BC Binwal ji | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
2. | 29-11-2016 | Chainage 10+290 | Checking of camber & density by CE Er BC C Binwal | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
3. | 01-10-2015 | 00-850 | BC work in progress | Anil Kumar | JE | UEAP R&B Nainital | See Pic |
4. | 22-07-2015 | 28-800 | R/w-damaj do to rain | Anil Kumar | JE | UEAP R&B Nainital | See Pic |
5. | 22-07-2015 | 25-650 | R/w-damaj do to rain | Anil Kumar | JE | UEAP R&B Nainital | See Pic |
6. | 09-07-2015 | 29+550 | B/W damaged by running slip | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
7. | 09-07-2015 | 29+650 | Excavation for B/W | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
8. | 20-06-2015 | Near University Gate | SDBC laying | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
9. | 20-06-2015 | Near Eco cave park nainital | Compaction of BM | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
10. | 19-06-2015 | 0+200 | Rolling of SDBC | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
11. | 19-06-2015 | Chainage 0 + 350 | SDBC laying near TRC Sukhatal Nainital | Rajiv Gururani | EE | DEA ADB Nainital | See Pic |
12. | 19-06-2015 | Chainage 0+200 | SDBC laying in the start point of Nainital Kaladhungi Motor Road | Rajiv Gururani | EE | DEA ADB Nainital | See Pic |
13. | 17-06-2015 | Chainage 0+120 | BM work in Nainital kaladhungi Motor Road start point | Rajiv Gururani | EE | DEA ADB Nainital | See Pic |
14. | 17-06-2015 | Chainage 0+100 | BM started in the start point of Nainital Kaladhungi Motor Road | Rajiv Gururani | EE | DEA ADB Nainital | See Pic |
15. | 26-05-2015 | Chainage Km 24.250 | K c dr | Rajiv Gururani | EE | DEA ADB Nainital | See Pic |
16. | 21-05-2015 | 14+125 | Construction of B/W | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
17. | 10-05-2015 | Chanage 26.500 | S D B C work in progress | Rajiv Gururani | EE | DEA ADB Nainital | See Pic |
18. | 10-05-2015 | Chainage 26.450 | S D B C work in progress | Rajiv Gururani | EE | DEA ADB Nainital | See Pic |
19. | 09-05-2015 | Chainge 23.700 | S D B C work in progress | Rajiv Gururani | EE | DEA ADB Nainital | See Pic |
20. | 09-05-2015 | Chainage 23.700 | S D B C work near Ghatgarh in Nainital kaladhungi road in progress | Rajiv Gururani | EE | DEA ADB Nainital | See Pic |
|
|