Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UEAP/PWD/C1 Agreement signed
Project: UEAP-RB Package No.: 1001 Package Name: UEAP/PWD/C1 Sanction Cost: 710.00  lakhs
District: Nainital Block: Kotabagh Constituency: Kaladhungi Circle:
DEA: DEA UEAP Nainital DSC: CCEE Group India Pvt.Ltd DSC Scope: Design & Supervision No.of Sub project : 2
Subproject in this package
1  5901   Kaladhungi- Kotabagh-Belpadav Road (7.000 KM.) (completed)
2  5902   Nainital-Kaladhungi- Bajpur Doraha Road (21.500 KM.) (completed)
Procurement:
Package No.: 1001        Package Name: UEAP/PWD/C1        Tender Date: 13-01-2014        Current Status: Agreement signed        Achieved on Date: 21-04-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C1        Contractor Name: Woodhill Infrastructure Ltd       
Start Date: 16-06-2014        Intended Completion Date: 18-01-2016        Original End Date:  18-09-2015
Total Bond Cost: 58834744.2 (588.35 lakhs)        Variation Cost: 8740028.90 (87.4 lakhs)     Hence Total Bond Cost is   67574773.1 (675.75 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 1000178 for 34 days        LD Analysis for Milestone2: calculated LD is Rs 1706186 for 58 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.BM i/c Prime Coat, Tack Coat1.86 KM38.711.37 KM1.37 KM8.438.71
2.SDBC i/c Tackcoat21.05 KM296.6521.55 KM21.55 KM64.76296.65
3.Culverts/Scupper 5.00 No11.836.00 No6.00 No2.6111.83
4.Road Furniture156.00 No33.11156.00 No156.00 No7.9833.11
5.Hill side Cutting & Slip clearence0.34 KM0.970.34 KM0.34 KM0.240.97
6.R/Wall, B/ Wall Type Protection works910.00 m56.892773.00 m2773.00 m13.8556.89
7.Cause Way4.00 No7.524.00 No4.00 No1.837.52
8.longitudinal Drain15113.00 m1.3615580.00 m15580.00 m0.331.36
Total Amount: 447.04 100   447.04
Remarks: No Remarks       Work Program Made On: 17-04-2015       Updation of work program on: 25-05-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.27-April-2015196.00  lakhs
2.27-June-2015120.70  lakhs
3.30-October-2015138.27  lakhs
4.21-March-2016135.20  lakhs
5.15-June-201760.86  lakhs
Total 651.03  lakhs
% Payment 96.34 %
Advance Amount:  58.00  lakhs        Recovered Amount:  58.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 68     No. of Test Done : 68      No. of Test Passed : 66      No. of Test Failed : 0   Test report of this package
Number of Pics Available on Web Repository: 34
Number of Notice(s) issued: 73

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.29-11-2016Chainage 3+008Checking of core by CE Hld Er BC Binwal jiRajiv GururaniEEUEAP R&B Nainital See Pic
2.29-11-2016Chainage 10+290Checking of camber & density by CE Er BC C BinwalRajiv GururaniEEUEAP R&B Nainital See Pic
3.01-10-201500-850BC work in progressAnil KumarJEUEAP R&B Nainital See Pic
4.22-07-201528-800R/w-damaj do to rainAnil KumarJEUEAP R&B Nainital See Pic
5.22-07-201525-650R/w-damaj do to rainAnil KumarJEUEAP R&B Nainital See Pic
6.09-07-201529+550B/W damaged by running slipLalit TiwariAEDEA ADB Nainital See Pic
7.09-07-201529+650Excavation for B/WLalit TiwariAEDEA ADB Nainital See Pic
8.20-06-2015Near University GateSDBC layingLalit TiwariAEDEA ADB Nainital See Pic
9.20-06-2015Near Eco cave park nainitalCompaction of BMLalit TiwariAEDEA ADB Nainital See Pic
10.19-06-20150+200Rolling of SDBCLalit TiwariAEDEA ADB Nainital See Pic
11.19-06-2015Chainage 0 + 350SDBC laying near TRC Sukhatal NainitalRajiv GururaniEEDEA ADB Nainital See Pic
12.19-06-2015Chainage 0+200SDBC laying in the start point of Nainital Kaladhungi Motor RoadRajiv GururaniEEDEA ADB Nainital See Pic
13.17-06-2015Chainage 0+120BM work in Nainital kaladhungi Motor Road start pointRajiv GururaniEEDEA ADB Nainital See Pic
14.17-06-2015Chainage 0+100BM started in the start point of Nainital Kaladhungi Motor RoadRajiv GururaniEEDEA ADB Nainital See Pic
15.26-05-2015Chainage Km 24.250K c drRajiv GururaniEEDEA ADB Nainital See Pic
16.21-05-201514+125Construction of B/WLalit TiwariAEDEA ADB Nainital See Pic
17.10-05-2015Chanage 26.500S D B C work in progressRajiv GururaniEEDEA ADB Nainital See Pic
18.10-05-2015Chainage 26.450S D B C work in progressRajiv GururaniEEDEA ADB Nainital See Pic
19.09-05-2015Chainge 23.700S D B C work in progressRajiv GururaniEEDEA ADB Nainital See Pic
20.09-05-2015Chainage 23.700S D B C work near Ghatgarh in Nainital kaladhungi road in progressRajiv GururaniEEDEA ADB Nainital See Pic