Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/02/36/RD/089 Agreement signed
Project: UDRP-RB Package No.: 100 Package Name: UDRP/PWD/02/36/RD/089 Sanction Cost: 474.31  lakhs
District: Chamoli Block: Ghat Constituency: Tharali Circle: Rudraprayag WB Circle
DEA: DEA Gopeshwar DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  1239   Ghat Baanjbagar Telan Motor Road (7.800 KM.) (completed)
Procurement:
Package No.: 100        Package Name: UDRP/PWD/02/36/RD/089        Tender Date: 18-02-2015        Current Status: Agreement signed        Achieved on Date: 04-06-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/02/36/RD/089        Contractor Name: Surat Singh & Sons       
Start Date: 11-06-2015        Intended Completion Date: 03-06-2017        Original End Date:  10-09-2016
Total Bond Cost: 38580821.75 (385.81 lakhs)        Variation Cost: 4096845.07 (40.97 lakhs)     Hence Total Bond Cost is   42677666.82 (426.78 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 752310 for 39 days        LD Analysis for Milestone2: calculated LD is Rs 1311720 for 68 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence7.80 KM1.677.80 KM7.80 KM0.541.67
2.R/Wall, B/ Wall Type Protection works1110.00 m64.141207.00 m1207.00 m20.6864.14
3.G-23.00 KM3.233.00 KM3.00 KM1.043.23
4.G-35.00 KM38.225.00 KM5.00 KM12.3238.22
5.PC/CC i/c Prime Coat, Tack Coat7.80 KM93.687.80 KM7.80 KM30.293.68
6.Culverts/Scupper 25.00 No67.9725.00 No25.00 No21.9167.97
7.longitudinal Drain7500.00 m38.007500.00 m7500.00 m12.2538.00
8.Parapet210.00 No1.00300.00 No300.00 No0.321.00
9.Road Furniture125.00 No2.29125.00 No125.00 No0.742.29
Total Amount: 310.2 100   310.2
Remarks: No Remarks       Work Program Made On: 13-07-2015       Updation of work program on: 24-05-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.31-October-201531.71  lakhs
2.30-November-201528.82  lakhs
3.26-December-201522.80  lakhs
4.29-February-201639.84  lakhs
5.02-May-201642.55  lakhs
6.30-June-201633.86  lakhs
7.14-July-201640.64  lakhs
8.17-December-201620.95  lakhs
9.30-December-201618.29  lakhs
10.31-March-201724.98  lakhs
11.01-June-201744.98  lakhs
12.12-October-201711.94  lakhs
13.27-November-201724.19  lakhs
14.28-February-201839.93  lakhs
Total 425.48  lakhs
% Payment 99.7 %
Advance Amount:  34.82  lakhs        Recovered Amount:  34.82  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 172     No. of Test Done : 200      No. of Test Passed : 167      No. of Test Failed : 33   Test report of this package
Number of Pics Available on Web Repository: 189
Number of Notice(s) issued: 95

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.02-07-20170.135Inter locking work in progressAshwani KumarREDSC4 R&B WB Chamoli See Pic
2.08-03-2017Ch-2.525Site visitPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
3.08-03-2017Ch- 2.580Thickness checking for pcPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
4.08-03-2017Ch-3.400Drain ExcavationPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
5.05-03-20173.200Site Visit by C.E. Sir ,S.E. Sir & E.E. SirMuhammad Munazir AnsariJEUDRP R&B Chamoli See Pic
6.02-02-2017Ch-5.825K.C. drain c typePramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
7.02-02-2017Ch-3.100R/W RR.DryPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
8.12-11-2016Ch-5.300Seal coat RectifyPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
9.25-10-2016Chainage-5.850kmPc laying workManish RanaJEUDRP R&B Gopeshwar See Pic
10.25-10-2016Chainage-5.860kmTack coat laying workManish RanaJEUDRP R&B Gopeshwar See Pic
11.25-10-2016Chainage-5.865kmPc laying workManish RanaJEUDRP R&B Gopeshwar See Pic
12.25-10-2016Chainage-5.825KmPc rolling workManish RanaJEUDRP R&B Gopeshwar See Pic
13.25-10-2016Chainage-5.900kmSeal coat rolling workManish RanaJEUDRP R&B Gopeshwar See Pic
14.19-10-2016Chainage-5.320kmParapet construction workManish RanaJEUDRP R&B Gopeshwar See Pic
15.18-10-20165.650Seal coat work in progressAshwani KumarREDSC4 R&B WB Chamoli See Pic
16.18-10-20165.650Bitumen content testAshwani KumarREDSC4 R&B WB Chamoli See Pic
17.17-10-2016Chainage-4.320Seal coat bitumen extractionManish RanaJEUDRP R&B Gopeshwar See Pic
18.17-10-2016Chainage.4.320Temperature of seal coatManish RanaJEUDRP R&B Gopeshwar See Pic
19.17-10-2016Chainage4.300Seal coat rolling workManish RanaJEUDRP R&B Gopeshwar See Pic
20.17-10-2016Ch.4.040kmSeal coat rolling workManish RanaJEUDRP R&B Gopeshwar See Pic