UDRP/PWD/02/36/RD/089
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
100 |
Package Name: |
UDRP/PWD/02/36/RD/089 |
Sanction Cost: |
474.31 lakhs |
District: |
Chamoli |
Block: |
Ghat |
Constituency: |
Tharali |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Gopeshwar |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 1239 Ghat Baanjbagar Telan Motor Road (7.800 KM.) (completed) |
|
Procurement: |
Package No.: 100
Package Name: UDRP/PWD/02/36/RD/089
Tender Date: 18-02-2015
Current Status: Agreement signed
Achieved on Date: 04-06-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/02/36/RD/089
Contractor Name: Surat Singh & Sons
|
Start Date: 11-06-2015
Intended Completion Date: 03-06-2017
Original End Date: 10-09-2016
|
Total Bond Cost: 38580821.75 (385.81 lakhs)
Variation Cost: 4096845.07 (40.97 lakhs) Hence Total Bond Cost is 42677666.82 (426.78 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 752310 for 39 days
LD Analysis for Milestone2: calculated LD is Rs 1311720 for 68 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 7.80 KM | 1.67 | 7.80 KM | 7.80 KM | 0.54 | 1.67 | 2. | R/Wall, B/ Wall Type Protection works | 1110.00 m | 64.14 | 1207.00 m | 1207.00 m | 20.68 | 64.14 | 3. | G-2 | 3.00 KM | 3.23 | 3.00 KM | 3.00 KM | 1.04 | 3.23 | 4. | G-3 | 5.00 KM | 38.22 | 5.00 KM | 5.00 KM | 12.32 | 38.22 | 5. | PC/CC i/c Prime Coat, Tack Coat | 7.80 KM | 93.68 | 7.80 KM | 7.80 KM | 30.2 | 93.68 | 6. | Culverts/Scupper | 25.00 No | 67.97 | 25.00 No | 25.00 No | 21.91 | 67.97 | 7. | longitudinal Drain | 7500.00 m | 38.00 | 7500.00 m | 7500.00 m | 12.25 | 38.00 | 8. | Parapet | 210.00 No | 1.00 | 300.00 No | 300.00 No | 0.32 | 1.00 | 9. | Road Furniture | 125.00 No | 2.29 | 125.00 No | 125.00 No | 0.74 | 2.29 |
Total Amount: |
310.2 |
|
100 |
310.2 |
|
Remarks:
No Remarks
Work Program Made On:
13-07-2015
Updation of work program on:
24-05-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 31-October-2015 | 31.71 lakhs |
2. | 30-November-2015 | 28.82 lakhs |
3. | 26-December-2015 | 22.80 lakhs |
4. | 29-February-2016 | 39.84 lakhs |
5. | 02-May-2016 | 42.55 lakhs |
6. | 30-June-2016 | 33.86 lakhs |
7. | 14-July-2016 | 40.64 lakhs |
8. | 17-December-2016 | 20.95 lakhs |
9. | 30-December-2016 | 18.29 lakhs |
10. | 31-March-2017 | 24.98 lakhs |
11. | 01-June-2017 | 44.98 lakhs |
12. | 12-October-2017 | 11.94 lakhs |
13. | 27-November-2017 | 24.19 lakhs |
14. | 28-February-2018 | 39.93 lakhs |
Total |
425.48 lakhs |
% Payment |
99.7 % |
|
Advance Amount: 34.82 lakhs
Recovered Amount: 34.82 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 189 |
Number of Notice(s) issued: 95 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 02-07-2017 | 0.135 | Inter locking work in progress | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
2. | 08-03-2017 | Ch-2.525 | Site visit | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
3. | 08-03-2017 | Ch- 2.580 | Thickness checking for pc | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
4. | 08-03-2017 | Ch-3.400 | Drain Excavation | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
5. | 05-03-2017 | 3.200 | Site Visit by C.E. Sir ,S.E. Sir & E.E. Sir | Muhammad Munazir Ansari | JE | UDRP R&B Chamoli | See Pic |
6. | 02-02-2017 | Ch-5.825 | K.C. drain c type | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
7. | 02-02-2017 | Ch-3.100 | R/W RR.Dry | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
8. | 12-11-2016 | Ch-5.300 | Seal coat Rectify | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
9. | 25-10-2016 | Chainage-5.850km | Pc laying work | Manish Rana | JE | UDRP R&B Gopeshwar | See Pic |
10. | 25-10-2016 | Chainage-5.860km | Tack coat laying work | Manish Rana | JE | UDRP R&B Gopeshwar | See Pic |
11. | 25-10-2016 | Chainage-5.865km | Pc laying work | Manish Rana | JE | UDRP R&B Gopeshwar | See Pic |
12. | 25-10-2016 | Chainage-5.825Km | Pc rolling work | Manish Rana | JE | UDRP R&B Gopeshwar | See Pic |
13. | 25-10-2016 | Chainage-5.900km | Seal coat rolling work | Manish Rana | JE | UDRP R&B Gopeshwar | See Pic |
14. | 19-10-2016 | Chainage-5.320km | Parapet construction work | Manish Rana | JE | UDRP R&B Gopeshwar | See Pic |
15. | 18-10-2016 | 5.650 | Seal coat work in progress | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
16. | 18-10-2016 | 5.650 | Bitumen content test | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
17. | 17-10-2016 | Chainage-4.320 | Seal coat bitumen extraction | Manish Rana | JE | UDRP R&B Gopeshwar | See Pic |
18. | 17-10-2016 | Chainage.4.320 | Temperature of seal coat | Manish Rana | JE | UDRP R&B Gopeshwar | See Pic |
19. | 17-10-2016 | Chainage4.300 | Seal coat rolling work | Manish Rana | JE | UDRP R&B Gopeshwar | See Pic |
20. | 17-10-2016 | Ch.4.040km | Seal coat rolling work | Manish Rana | JE | UDRP R&B Gopeshwar | See Pic |
|
|