Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/08/05/RD/010 Agreement signed
Project: UDRP-RB Package No.: 10 Package Name: UDRP/PWD/08/05/RD/010 Sanction Cost: 1242.49  lakhs
District: Bageshwar Block: Bageshwar Constituency: Kapkote Circle: Pithoragarh WB Circle
DEA: DEA Bageshwar DSC: Royal Haskoning DHV DSC Scope: only Supervision No.of Sub project : 1
Subproject in this package
1  1111   Kanda-Saniudiay-Rawatsera MR (20.000 KM.) (completed)
Procurement:
Package No.: 10        Package Name: UDRP/PWD/08/05/RD/010        Tender Date: 03-05-2014        Current Status: Agreement signed        Achieved on Date: 15-09-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/08/05/RD/010        Contractor Name: ESPAN Infrastructure Ltd       
Start Date: 22-09-2014        Intended Completion Date: 31-07-2016        Original End Date:  21-12-2015
Total Bond Cost: 103151291 (1031.51 lakhs)        Variation Cost: 7698581.22 (76.99 lakhs)     Hence Total Bond Cost is   110849872.22 (1108.5 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 3507168 for 68 days        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence3.00 KM33.903.00 KM3.00 KM3.0933.90
2.R/Wall, B/ Wall Type Protection works1200.00 m97.771200.00 m1200.00 m8.9297.77
3.G-32.88 KM15.782.88 KM2.88 KM1.4415.78
4.BM i/c Prime Coat, Tack Coat20.00 KM500.6520.00 KM20.00 KM45.65500.65
5.SDBC i/c Tackcoat20.00 KM273.0720.00 KM20.00 KM24.9273.07
6.Cause Way4.00 No17.994.00 No4.00 No1.6417.99
7.Culverts/Scupper 22.00 No19.3222.00 No22.00 No1.7619.32
8.longitudinal Drain16000.00 m17.2716000.00 m16000.00 m1.5817.27
9.Crash Barrier4006.00 m101.754006.00 m4006.00 m9.28101.75
10.Parapet99.00 No4.6999.00 No99.00 No0.434.69
11.Road Furniture34.00 No14.52551.00 No551.00 No1.3214.52
Total Amount: 1096.71 100   1096.71
Remarks: No Remarks       Work Program Made On: 01-10-2014       Updation of work program on: 29-11-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.28-May-201526.44  lakhs
2.29-June-2015187.28  lakhs
3.26-August-201572.46  lakhs
4.12-October-2015198.15  lakhs
5.31-October-2015104.50  lakhs
6.04-December-2015336.35  lakhs
7.28-July-201639.40  lakhs
8.08-December-20161.52  lakhs
9.22-February-20170.29  lakhs
10.31-March-2017143.80  lakhs
Total 1110.19  lakhs
% Payment 100.15 %
Advance Amount:  637.06  lakhs        Recovered Amount:  637.06  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 958     No. of Test Done : 883      No. of Test Passed : 855      No. of Test Failed : 28   Test report of this package
Number of Pics Available on Web Repository: 187
Number of Notice(s) issued: 106

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.07-12-2020A1 abutment at Sada ThaliWork in progressDeepak PantSite supervisiorUDRP AF Irrigation birahi See Pic
2.17-10-2016Ch 1.200Site visit by mission world bankSanjeev BhattAEUDRP R&B Bageshwar See Pic
3.17-10-2016Ch 0. 150Site visit by world bank missionSanjeev BhattAEUDRP R&B Bageshwar See Pic
4.17-10-2016Ch 0. 035Site inspection by mission world bankSanjeev BhattAEUDRP R&B Bageshwar See Pic
5.23-09-2016Km 20Road surface at hp bendManoj SharmaJEUDRP R&B Bageshwar See Pic
6.23-09-2016Km 20Top view of km 20Manoj SharmaJEUDRP R&B Bageshwar See Pic
7.23-09-2016Ch.13.100Road surfaceManoj SharmaJEUDRP R&B Bageshwar See Pic
8.23-09-2016Km 10Road surfaceManoj SharmaJEUDRP R&B Bageshwar See Pic
9.23-09-2016Km 6Road surfaceManoj SharmaJEUDRP R&B Bageshwar See Pic
10.23-09-2016Ch.5.300Road surfaceManoj SharmaJEUDRP R&B Bageshwar See Pic
11.23-09-2016Ch.1.315Casting of causeway(cause way work complete)Manoj SharmaJEUDRP R&B Bageshwar See Pic
12.23-09-2016Ch.0.600Road surface after protection work.Manoj SharmaJEUDRP R&B Bageshwar See Pic
13.23-09-2016Ch.0. 450Road surface after protection and road furniture work.Manoj SharmaJEUDRP R&B Bageshwar See Pic
14.22-09-20161+310Causeway work on progressHarish ChandraJEUDRP R&B Bageshwar See Pic
15.08-09-2016Ch. 20.00SE sir and CME sir inspection the roadManoj SharmaJEUDRP R&B Bageshwar See Pic
16.08-09-2016Ch 1.315SE sir and CME sir inspection the roadManoj SharmaJEUDRP R&B Bageshwar See Pic
17.04-09-2016Ch. 1.650Balance work of interlocking tiles .contractor does take a interest to complete the work.Manoj SharmaJEUDRP R&B Bageshwar See Pic
18.24-08-201600+050Site visit World Bank mission at PKG 10 KSR motor road in Bageshwar DistirctRishi RamQCDSC5 R&B WB Bageshwar See Pic
19.13-08-2016Ch. 10. 730Rejected parapets due poor qualityManoj SharmaJEUDRP R&B Bageshwar See Pic
20.13-08-2016Ch. 19. 930Rejected Parapets due to poor quality.Manoj SharmaJEUDRP R&B Bageshwar See Pic