UDRP/PWD/08/05/RD/010
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
10 |
Package Name: |
UDRP/PWD/08/05/RD/010 |
Sanction Cost: |
1242.49 lakhs |
District: |
Bageshwar |
Block: |
Bageshwar |
Constituency: |
Kapkote |
Circle: |
Pithoragarh WB Circle |
DEA: |
DEA Bageshwar |
DSC: |
Royal Haskoning DHV |
DSC Scope: |
only Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 1111 Kanda-Saniudiay-Rawatsera MR (20.000 KM.) (completed) |
|
Procurement: |
Package No.: 10
Package Name: UDRP/PWD/08/05/RD/010
Tender Date: 03-05-2014
Current Status: Agreement signed
Achieved on Date: 15-09-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/08/05/RD/010
Contractor Name: ESPAN Infrastructure Ltd
|
Start Date: 22-09-2014
Intended Completion Date: 31-07-2016
Original End Date: 21-12-2015
|
Total Bond Cost: 103151291 (1031.51 lakhs)
Variation Cost: 7698581.22 (76.99 lakhs) Hence Total Bond Cost is 110849872.22 (1108.5 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 3507168 for 68 days
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 3.00 KM | 33.90 | 3.00 KM | 3.00 KM | 3.09 | 33.90 | 2. | R/Wall, B/ Wall Type Protection works | 1200.00 m | 97.77 | 1200.00 m | 1200.00 m | 8.92 | 97.77 | 3. | G-3 | 2.88 KM | 15.78 | 2.88 KM | 2.88 KM | 1.44 | 15.78 | 4. | BM i/c Prime Coat, Tack Coat | 20.00 KM | 500.65 | 20.00 KM | 20.00 KM | 45.65 | 500.65 | 5. | SDBC i/c Tackcoat | 20.00 KM | 273.07 | 20.00 KM | 20.00 KM | 24.9 | 273.07 | 6. | Cause Way | 4.00 No | 17.99 | 4.00 No | 4.00 No | 1.64 | 17.99 | 7. | Culverts/Scupper | 22.00 No | 19.32 | 22.00 No | 22.00 No | 1.76 | 19.32 | 8. | longitudinal Drain | 16000.00 m | 17.27 | 16000.00 m | 16000.00 m | 1.58 | 17.27 | 9. | Crash Barrier | 4006.00 m | 101.75 | 4006.00 m | 4006.00 m | 9.28 | 101.75 | 10. | Parapet | 99.00 No | 4.69 | 99.00 No | 99.00 No | 0.43 | 4.69 | 11. | Road Furniture | 34.00 No | 14.52 | 551.00 No | 551.00 No | 1.32 | 14.52 |
Total Amount: |
1096.71 |
|
100 |
1096.71 |
|
Remarks:
No Remarks
Work Program Made On:
01-10-2014
Updation of work program on:
29-11-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 28-May-2015 | 26.44 lakhs |
2. | 29-June-2015 | 187.28 lakhs |
3. | 26-August-2015 | 72.46 lakhs |
4. | 12-October-2015 | 198.15 lakhs |
5. | 31-October-2015 | 104.50 lakhs |
6. | 04-December-2015 | 336.35 lakhs |
7. | 28-July-2016 | 39.40 lakhs |
8. | 08-December-2016 | 1.52 lakhs |
9. | 22-February-2017 | 0.29 lakhs |
10. | 31-March-2017 | 143.80 lakhs |
Total |
1110.19 lakhs |
% Payment |
100.15 % |
|
Advance Amount: 637.06 lakhs
Recovered Amount: 637.06 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 187 |
Number of Notice(s) issued: 106 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 07-12-2020 | A1 abutment at Sada Thali | Work in progress | Deepak Pant | Site supervisior | UDRP AF Irrigation birahi | See Pic |
2. | 17-10-2016 | Ch 1.200 | Site visit by mission world bank | Sanjeev Bhatt | AE | UDRP R&B Bageshwar | See Pic |
3. | 17-10-2016 | Ch 0. 150 | Site visit by world bank mission | Sanjeev Bhatt | AE | UDRP R&B Bageshwar | See Pic |
4. | 17-10-2016 | Ch 0. 035 | Site inspection by mission world bank | Sanjeev Bhatt | AE | UDRP R&B Bageshwar | See Pic |
5. | 23-09-2016 | Km 20 | Road surface at hp bend | Manoj Sharma | JE | UDRP R&B Bageshwar | See Pic |
6. | 23-09-2016 | Km 20 | Top view of km 20 | Manoj Sharma | JE | UDRP R&B Bageshwar | See Pic |
7. | 23-09-2016 | Ch.13.100 | Road surface | Manoj Sharma | JE | UDRP R&B Bageshwar | See Pic |
8. | 23-09-2016 | Km 10 | Road surface | Manoj Sharma | JE | UDRP R&B Bageshwar | See Pic |
9. | 23-09-2016 | Km 6 | Road surface | Manoj Sharma | JE | UDRP R&B Bageshwar | See Pic |
10. | 23-09-2016 | Ch.5.300 | Road surface | Manoj Sharma | JE | UDRP R&B Bageshwar | See Pic |
11. | 23-09-2016 | Ch.1.315 | Casting of causeway(cause way work complete) | Manoj Sharma | JE | UDRP R&B Bageshwar | See Pic |
12. | 23-09-2016 | Ch.0.600 | Road surface after protection work. | Manoj Sharma | JE | UDRP R&B Bageshwar | See Pic |
13. | 23-09-2016 | Ch.0. 450 | Road surface after protection and road furniture work. | Manoj Sharma | JE | UDRP R&B Bageshwar | See Pic |
14. | 22-09-2016 | 1+310 | Causeway work on progress | Harish Chandra | JE | UDRP R&B Bageshwar | See Pic |
15. | 08-09-2016 | Ch. 20.00 | SE sir and CME sir inspection the road | Manoj Sharma | JE | UDRP R&B Bageshwar | See Pic |
16. | 08-09-2016 | Ch 1.315 | SE sir and CME sir inspection the road | Manoj Sharma | JE | UDRP R&B Bageshwar | See Pic |
17. | 04-09-2016 | Ch. 1.650 | Balance work of interlocking tiles .contractor does take a interest to complete the work. | Manoj Sharma | JE | UDRP R&B Bageshwar | See Pic |
18. | 24-08-2016 | 00+050 | Site visit World Bank mission at PKG 10 KSR motor road in Bageshwar Distirct | Rishi Ram | QC | DSC5 R&B WB Bageshwar | See Pic |
19. | 13-08-2016 | Ch. 10. 730 | Rejected parapets due poor quality | Manoj Sharma | JE | UDRP R&B Bageshwar | See Pic |
20. | 13-08-2016 | Ch. 19. 930 | Rejected Parapets due to poor quality. | Manoj Sharma | JE | UDRP R&B Bageshwar | See Pic |
|
|