Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/03/39/RD/001 Agreement signed
Project: UDRP-RB Package No.: 1 Package Name: UDRP/PWD/03/39/RD/001 Sanction Cost: 349.00  lakhs
District: Rudraprayag Block: August Muni Constituency: Rudraprayag Circle: Rudraprayag WB Circle
DEA: DEA Guptkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: only Supervision No.of Sub project : 1
Subproject in this package
1  2501   Kandai-Kamoldi-Molkhakhal Motor Road (20.780 KM.) (completed)
Procurement:
Package No.: 1        Package Name: UDRP/PWD/03/39/RD/001        Tender Date: 20-01-2014        Current Status: Agreement signed        Achieved on Date: 17-04-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/03/39/RD/001        Contractor Name: R.G. Buildwell.       
Start Date: 24-04-2014        Intended Completion Date: 13-12-2015        Original End Date:  23-07-2015
Total Bond Cost: 31914076 (319.14 lakhs)        Variation Cost: -13546676.75 (-135.47 lakhs)     Hence Total Bond Cost is   18367399.25 (183.67 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 2345679 for 147 days        LD Analysis for Milestone2: calculated LD is Rs 3478626 for +218 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence0.90 KM11.200.90 KM0.90 KM6.1211.20
2.R/Wall, B/ Wall Type Protection works778.00 m73.42778.00 m778.00 m40.0873.42
3.GSB/RBI/G-10.27 KM1.010.27 KM0.27 KM0.551.01
4.G-30.11 KM0.360.11 KM0.11 KM0.20.36
5.PC/CC i/c Prime Coat, Tack Coat0.75 KM6.250.75 KM0.75 KM3.416.25
6.Cause Way5.00 No4.535.00 No5.00 No2.474.53
7.Culverts/Scupper 4.00 No8.254.00 No4.00 No4.58.25
8.longitudinal Drain7585.00 m15.877585.00 m7585.00 m8.6715.87
9.Crash Barrier1970.00 m59.101970.00 m1970.00 m32.2759.10
10.Parapet66.00 No1.2566.00 No66.00 No0.681.25
11.Road Furniture21.00 No1.9321.00 No21.00 No1.051.93
Total Amount: 183.17 100   183.17
Remarks: no remark       Work Program Made On: 20-08-2014       Updation of work program on: 16-04-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.27-September-20145.61  lakhs
2.30-November-20144.46  lakhs
3.30-December-201411.53  lakhs
4.28-February-201515.62  lakhs
5.27-March-201523.59  lakhs
6.31-March-201550.32  lakhs
7.30-May-201515.86  lakhs
8.28-August-201512.68  lakhs
9.28-September-201516.44  lakhs
10.27-October-201622.67  lakhs
Total 178.78  lakhs
% Payment 97.34 %
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 42     No. of Test Done : 28      No. of Test Passed : 23      No. of Test Failed : 5   Test report of this package
Number of Pics Available on Web Repository: 92
Number of Notice(s) issued: 123

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.12-05-2016Ch. 4.000BM / SDBC depressionPratyush ChoudharyMIS ExpertDSC1 R&B WB See Pic
2.24-12-20150.050PC Checking by DPM Mr. DayanandR S RajputREDSC1 R&B WB Rudraprayag See Pic
3.24-12-201500.725Solder filling & drain cleaning workMahtab Alam KhanSite SupervisorDSC1 R&B WB Rudraprayag See Pic
4.24-12-201500.725Solder filling & drain cleaning workMahtab Alam KhanSite SupervisorDSC1 R&B WB Rudraprayag See Pic
5.24-12-2015+750earth drain making of road side and patri filling workVineet KumarJEUDRP R&B Guptkashi See Pic
6.26-11-2015.310SDBC In progressR S RajputREDSC1 R&B WB Rudraprayag See Pic
7.26-11-2015HMPSDBC Mix LoadingSaroj KumarQCDSC1 R&B WB Rudraprayag See Pic
8.24-11-201518+800 settelment areaexcavation of plumVineet KumarJEUDRP R&B Guptkashi See Pic
9.28-10-2015+11.200scupper 2nd half slab steel binding workVineet KumarJEUDRP R&B Guptkashi See Pic
10.28-10-2015+.250pc repair work demage reason of rain fallVineet KumarJEUDRP R&B Guptkashi See Pic
11.28-10-2015+.250pc repair work, damage pc to reason of rain fallVineet KumarJEUDRP R&B Guptkashi See Pic
12.25-10-201518.650NewdamagesinkingjoneS C TyagiEEDEA WB Guptkashi See Pic
13.25-10-201518.700NewdamagesinkingjoneS C TyagiEEDEA WB Guptkashi See Pic
14.25-10-2015Km14.375R/watkkmroadS C TyagiEEDEA WB Guptkashi See Pic
15.19-10-2015Site LabGradation of Stone DustSaroj KumarQCDSC1 R&B WB Rudraprayag See Pic
16.19-10-2015Site Lab at CH-10.900Lab EquipmentsSaroj KumarQCDSC1 R&B WB Rudraprayag See Pic
17.30-09-20155+400causeway cc 2nd partVineet KumarJEUDRP R&B Guptkashi See Pic
18.28-09-20155+400 causewaycause way castingVineet KumarJEUDRP R&B Guptkashi See Pic
19.28-09-201514+300wire crateVineet KumarJEUDRP R&B Guptkashi See Pic
20.28-09-2015cause way pcc 5+600causeway pcc 5+600Vineet KumarJEUDRP R&B Guptkashi See Pic