UDRP/PWD/03/39/RD/001
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
1 |
Package Name: |
UDRP/PWD/03/39/RD/001 |
Sanction Cost: |
349.00 lakhs |
District: |
Rudraprayag |
Block: |
August Muni |
Constituency: |
Rudraprayag |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Guptkashi |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
only Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 2501 Kandai-Kamoldi-Molkhakhal Motor Road (20.780 KM.) (completed) |
|
Procurement: |
Package No.: 1
Package Name: UDRP/PWD/03/39/RD/001
Tender Date: 20-01-2014
Current Status: Agreement signed
Achieved on Date: 17-04-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/03/39/RD/001
Contractor Name: R.G. Buildwell.
|
Start Date: 24-04-2014
Intended Completion Date: 13-12-2015
Original End Date: 23-07-2015
|
Total Bond Cost: 31914076 (319.14 lakhs)
Variation Cost: -13546676.75 (-135.47 lakhs) Hence Total Bond Cost is 18367399.25 (183.67 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 2345679 for 147 days
LD Analysis for Milestone2: calculated LD is Rs 3478626 for +218 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 0.90 KM | 11.20 | 0.90 KM | 0.90 KM | 6.12 | 11.20 | 2. | R/Wall, B/ Wall Type Protection works | 778.00 m | 73.42 | 778.00 m | 778.00 m | 40.08 | 73.42 | 3. | GSB/RBI/G-1 | 0.27 KM | 1.01 | 0.27 KM | 0.27 KM | 0.55 | 1.01 | 4. | G-3 | 0.11 KM | 0.36 | 0.11 KM | 0.11 KM | 0.2 | 0.36 | 5. | PC/CC i/c Prime Coat, Tack Coat | 0.75 KM | 6.25 | 0.75 KM | 0.75 KM | 3.41 | 6.25 | 6. | Cause Way | 5.00 No | 4.53 | 5.00 No | 5.00 No | 2.47 | 4.53 | 7. | Culverts/Scupper | 4.00 No | 8.25 | 4.00 No | 4.00 No | 4.5 | 8.25 | 8. | longitudinal Drain | 7585.00 m | 15.87 | 7585.00 m | 7585.00 m | 8.67 | 15.87 | 9. | Crash Barrier | 1970.00 m | 59.10 | 1970.00 m | 1970.00 m | 32.27 | 59.10 | 10. | Parapet | 66.00 No | 1.25 | 66.00 No | 66.00 No | 0.68 | 1.25 | 11. | Road Furniture | 21.00 No | 1.93 | 21.00 No | 21.00 No | 1.05 | 1.93 |
Total Amount: |
183.17 |
|
100 |
183.17 |
|
Remarks:
no remark
Work Program Made On:
20-08-2014
Updation of work program on:
16-04-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 27-September-2014 | 5.61 lakhs |
2. | 30-November-2014 | 4.46 lakhs |
3. | 30-December-2014 | 11.53 lakhs |
4. | 28-February-2015 | 15.62 lakhs |
5. | 27-March-2015 | 23.59 lakhs |
6. | 31-March-2015 | 50.32 lakhs |
7. | 30-May-2015 | 15.86 lakhs |
8. | 28-August-2015 | 12.68 lakhs |
9. | 28-September-2015 | 16.44 lakhs |
10. | 27-October-2016 | 22.67 lakhs |
Total |
178.78 lakhs |
% Payment |
97.34 % |
|
Advance Amount: 0.00 lakhs
Recovered Amount: 0.00 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 92 |
Number of Notice(s) issued: 123 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 12-05-2016 | Ch. 4.000 | BM / SDBC depression | Pratyush Choudhary | MIS Expert | DSC1 R&B WB | See Pic |
2. | 24-12-2015 | 0.050 | PC Checking by DPM Mr. Dayanand | R S Rajput | RE | DSC1 R&B WB Rudraprayag | See Pic |
3. | 24-12-2015 | 00.725 | Solder filling & drain cleaning work | Mahtab Alam Khan | Site Supervisor | DSC1 R&B WB Rudraprayag | See Pic |
4. | 24-12-2015 | 00.725 | Solder filling & drain cleaning work | Mahtab Alam Khan | Site Supervisor | DSC1 R&B WB Rudraprayag | See Pic |
5. | 24-12-2015 | +750 | earth drain making of road side and patri filling work | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
6. | 26-11-2015 | .310 | SDBC In progress | R S Rajput | RE | DSC1 R&B WB Rudraprayag | See Pic |
7. | 26-11-2015 | HMP | SDBC Mix Loading | Saroj Kumar | QC | DSC1 R&B WB Rudraprayag | See Pic |
8. | 24-11-2015 | 18+800 settelment area | excavation of plum | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
9. | 28-10-2015 | +11.200 | scupper 2nd half slab steel binding work | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
10. | 28-10-2015 | +.250 | pc repair work demage reason of rain fall | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
11. | 28-10-2015 | +.250 | pc repair work, damage pc to reason of rain fall | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
12. | 25-10-2015 | 18.650 | Newdamagesinkingjone | S C Tyagi | EE | DEA WB Guptkashi | See Pic |
13. | 25-10-2015 | 18.700 | Newdamagesinkingjone | S C Tyagi | EE | DEA WB Guptkashi | See Pic |
14. | 25-10-2015 | Km14.375 | R/watkkmroad | S C Tyagi | EE | DEA WB Guptkashi | See Pic |
15. | 19-10-2015 | Site Lab | Gradation of Stone Dust | Saroj Kumar | QC | DSC1 R&B WB Rudraprayag | See Pic |
16. | 19-10-2015 | Site Lab at CH-10.900 | Lab Equipments | Saroj Kumar | QC | DSC1 R&B WB Rudraprayag | See Pic |
17. | 30-09-2015 | 5+400 | causeway cc 2nd part | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
18. | 28-09-2015 | 5+400 causeway | cause way casting | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
19. | 28-09-2015 | 14+300 | wire crate | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
20. | 28-09-2015 | cause way pcc 5+600 | causeway pcc 5+600 | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
|
|