Pic Id: 5867 Uid: 7109
Subproject: Srinagar-And-Pauri-Water-Supply-Scheme Phase1 District: Pauri
Data Collector: Rakesh Sharma Designation: Contractor Project Manager
Organisation: UEAP WS Pauri
Landmark: M30trial mix cub testing Remark: Trial mix cub testing
Date: 2015-07-16 11:22:47

Comments:


Concrete cube crushing for 7 days and 28 days to be ensured for the concreting.The equipment to have proper calibration.
By: Ashok Negi About Quality,Suggestions
on 17-October-2016 16:35 PM


Last Five Images

35869Subproject Alakapuri Kathiyal Sain Alaknanda in Chamoli on date 2019-05-08 13:39:41
35849Subproject Birahi Village RB Alaknanda in Chamoli on date 2019-05-06 10:55:58
35850Subproject Birahi Village RB Alaknanda in Chamoli on date 2019-05-06 11:00:08
32488Subproject Birsanikhal-Kota-Silsu-bhutnisi MR in Pauri on date 2018-08-24 13:29:11
32531Subproject Nainipatal Madmaley MR (Ch-7 to 13.162 Km) in Pithoragarh on date 2018-08-30 15:29:55

Random Images

24486
21792
24174
24592
35869
27331
32445
25419
26954

Leave a comment:

Pic Location Map

CAPTCHA code

Data at a Glance

  • Total no. of pics available in system
    33053
  • No. of pics got remarked.
    315
  • Total no. of pics recieved in this month.
    168
  • No. of pics got remarked in this month.
    3
© 2019 ukdisasterrecovery.in