Subproject: Uttarkashi-Water-Supply-Scheme District: Tehri
Data Collector: Monendra Singh Rana Designation: Construction supervisor
Organisation: DSC WS ADB Tehri
Landmark: Back side Gufiyara WTP Remark: Excavation and disposal of surplus earth work for retaining wall is in progress
Date: 2017-06-25 17:25:16

Comments:


Contractor, DSC and Executive Engineer, after repeated request as well as instructions, still the labors are seen without PPEs. Please ensure use of PPEs.
By: Nutan Gupta About Quality,Environment
on 06-October-2017 16:50 PM

DSC as well as Contractor please ensure the PPE as well as barricading and safety boards on the site.
By: Aparna Pandey About Social
on 03-July-2017 12:06 PM


Last Five Images

31367Subproject Charma Jaurasi Lakhatigaon in Pithoragarh on date 2018-03-29 15:13:49
31369Subproject Madkot Bauna in Pithoragarh on date 2018-03-30 15:41:32
31164Subproject Okadi Ana Lohar Chada Gairlekh MR Phase2 (Ch-6 to 12 Km) in Bageshwar on date 2018-02-17 11:51:30
31154Subproject Charma Jaurasi Lakhatigaon in Pithoragarh on date 2018-02-17 14:30:49
30975Subproject Kandai Kamoldi Molkakhal MR Phase2 (Ch-0 to 10 Km) in Rudraprayag on date 2018-01-25 16:44:09

Random Images

28901
5867
24522
25958
25048
29012
29141
21792
28881

Leave a comment:

Pic Location Map

CAPTCHA code

Data at a Glance

  • Total no. of pics available in system
    30689
  • No. of pics got remarked.
    281
  • Total no. of pics recieved in this month.
    49
  • No. of pics got remarked in this month.
    2
© 2018 ukdisasterrecovery.in