Image to be Discussed


28884

Pic Id: 28884 Uid: 3238
Subproject: Newgaon Sari Shrikalkhal Motor road phase 2 District: Uttarkashi
Data Collector: Chandra Lal Bharti Designation: JE
Organisation: UDRP R&B Uttarkashi
Landmark: 9/14 Remark: PC work in progress
Date: 2017-05-26 12:22:22

Comments:


I am giving instruction to contractor.
By: Chandra Lal Bharti About Environment
on 02-June-2017 13:09 PM

@ Contractor, DSC and Executive Engineer, please ensure that safety sign boards are placed at all work sites
By: Ashish Anthwal About Environment
on 31-May-2017 18:51 PM


Last Five Images

31679Subproject Bridge at Kalpeshwar on Helang-Urgam-Kalkeshuar Bridle Road in Chamoli on date 2018-06-15 12:01:58
31682Subproject Kandai Kamoldi Molkakhal MR Phase2 (Ch-0 to 10 Km) in Rudraprayag on date 2018-06-16 16:03:44
31690Subproject Bridge over indrawati river near Sada in Uttarkashi on date 2018-06-18 13:19:43
31691Subproject Bridge over Benakuli river near Khiro in Chamoli on date 2018-06-18 14:13:51
31694Subproject Batadhar Dhunarghat Motor Road in Chamoli on date 2018-06-19 15:35:03

Random Images

30895
24466
25468
28881
29050
24534
25563
28892
16137

Leave a comment:

Pic Location Map

CAPTCHA code

Data at a Glance

  • Total no. of pics available in system
    30937
  • No. of pics got remarked.
    287
  • Total no. of pics recieved in this month.
    41
  • No. of pics got remarked in this month.
    6
© 2018 ukdisasterrecovery.in