Pic Id: 25434 Uid: 7210 Subproject: Hybrid Huts at Auli District: Chamoli Data Collector: Gambhir Singh Designation: DPM Organisation: PIU UEAP Tourism Landmark: TRH Auli Remark: Finishing work at auli is in progress Date: 2016-11-19 09:17:20
Comments:
All environment and social compliances have been complied with by the concerned contractors at most of the sites.ACME who is not being complying the said compliances,has been instructed.
@ Contractor and Field PIU, reply to comment raised on December 8, 2016 is still awaited.
Contractor,
Has the labour been provided with adequate facilities especially of Sanitation?? As found missing during visit in October.
Contractor,
No Labour license, workmen insurance has been submitted for works under this package 5. This is total non compliance that even after reminders you are not submitting the required. Submit the same in a week's time.
Last Five Images
Subproject Bridge in KM-3 of Sisaldi Satpuli MR in Pauri on date 2022-01-30 15:54:58
Subproject 70 Mtr span motor bridge at Km-166 of Munshiyari motor road at hardiya nala. in Pithoragarh on date 2022-01-30 17:11:14
Subproject Khoja in Pithoragarh on date 2022-01-30 16:04:57
Subproject Bridge on Basutiya Dogda Motor Road (Km-1) in Nainital on date 2021-06-05 15:55:32
Subproject 60M Steel Truss Motor Bridge at KM-1 of Bhonsal Bheti MR in Pauri on date 2021-06-05 15:09:01