Pic Id: 25265 Uid: 1142
Subproject: Kapkot- Tehsil-Poling MR Phase2 District: Bageshwar
Data Collector: Jagdish Narayan Meena Designation: AE
Organisation: UDRP R&B Bageshwar
Landmark: Ch 4.000 Remark: Stacking of G1 stone
Date: 2016-11-12 16:33:45

Comments:


Superelevation was corrected as per requirement of specification before spreading of metal for WBM greading-1
By: Jagdish Narayan Meena About Quality
on 22-December-2016 12:08 PM

Contractor has been asked to provide super elevation in Sub grade at the curves before WBM work.
By: Naresh Mittal About Quality
on 02-December-2016 15:22 PM

On curve super elevation was not made in sub grade.Ensure proper super elevation must be made according to curve before WBM work.
By: Sunil kumar About Quality
on 16-November-2016 12:31 PM


Last Five Images

38544Subproject Bridge on Kapkot Pindari Glacier MR KM-13 in Bageshwar on date 2020-12-04 12:23:19
38417Subproject Bridge over Jalkur River on Bagi Gaun Gajna Bridle Road in Uttarkashi on date 2020-11-24 11:40:24
38783Subproject Bridge near Km-2 of Kund Kotla Motor Road at Kund Khad in Uttarkashi on date 2020-12-22 13:49:51
38413Subproject Tachla Naur Slope Motor Road KM-1 in Tehri on date 2020-11-23 15:29:52
38414Subproject Alakapuri Kathiyal Sain Alaknanda in Chamoli on date 2020-11-24 12:10:41

Random Images

24393
27547
31664
24634
24540
27433
24828
31694
26289

Leave a comment:

Pic Location Map

CAPTCHA code

Data at a Glance

  • Total no. of pics available in system
    38619
  • No. of pics got remarked.
    321
  • Total no. of pics recieved in this month.
    236
  • No. of pics got remarked in this month.
    0
© 2021 ukdisasterrecovery.in