Subproject: Madkot Bauna District: Pithoragarh
Data Collector: Dinesh Kumar Designation: RE
Organisation: DSC4 R&B WB Munsyari
Landmark: 6+540 Remark: Hill cutting
Date: 2016-10-24 09:31:46

Comments:


Due to more height of hill side cutting, some percentage of muck is overturn in the valley side during the cutting, we are trying to retain all muck at road level and dispose off in Dumping yard, land for dumping yard is taken from private land owner by the contractor.
By: Prem Prakash About Environment
on 18-December-2016 13:09 PM

muck disposal in private land landowner wants to level the land ,already agreement done between contractor and landowner
By: Dinesh Kumar About Environment
on 19-November-2016 10:19 AM

muck disposal in private land landowner wants to level the land ,already agreement done between contractor and landowner .
By: Dinesh Kumar About Environment
on 27-October-2016 14:11 PM

Ensure muck disposal as per ESMF
By: adarsh About Environment,Suggestions
on 26-October-2016 14:20 PM


Last Five Images

24755Subproject Ranari to Danda Majaf MR in Uttarkashi on date 2016-10-24 11:41:48
29855Subproject Bunga Malla Motor Road in Pauri on date 2017-09-18 10:09:06
29220Subproject Dyangar-Kathyatbara-Aare bypass MR in Bageshwar on date 2017-06-22 13:34:14
29571Subproject Didsari Bridge in Uttarkashi on date 2017-08-03 12:44:00
29534Subproject Didsari Bridge in Uttarkashi on date 2017-07-29 11:49:46

Random Images

25212
24592
28961
24720
17970
24699
20622
25105
24534

Leave a comment:

Pic Location Map

CAPTCHA code

Data at a Glance

  • Total no. of pics available in system
    29141
  • No. of pics got remarked.
    271
  • Total no. of pics recieved in this month.
    122
  • No. of pics got remarked in this month.
    3
© 2017 ukdisasterrecovery.in