Subproject: Sonla - Kandara - Maikhura Silangi MR District: Chamoli
Data Collector: Ankur Vishwas Designation: Contractor Site Engineer
Organisation: DSC1 R&B WB Chamoli
Landmark: Ch.27. 825 Remark: WBM work over G3 layer
Date: 2016-10-23 15:54:41

Comments:


labours are regularly using PPE,s at site.
By: Kirti Vardhan Negi About Social
on 14-March-2017 18:15 PM

Ask to Contractor r regarding complete use of PPE, Contractor ensure to use complete PPE. Labour use PPE on regular basis.
By: Ashwini Kumar About Social
on 17-January-2017 12:45 PM

Why laborers are not wearing PPE? CSE to please keep a close watch and ask the contractor to ensure the same,
By: Neha Dobhal About Social
on 27-October-2016 16:19 PM

There is no provision of screening material in G3 layer.Provision of binding material of PI 4 to 6 is in bond which is being used as per norms.
By: Kirti Vardhan Negi About Quality
on 27-October-2016 12:05 PM

Screening material seems to be not as per specification.
By: Ravinder Singh Anand About Quality
on 26-October-2016 13:32 PM


Last Five Images

31664Subproject Katpudiya Chhina Seraghat MR (Ch-0 to 13 Km) in Bageshwar on date 2018-05-31 15:39:00
31666Subproject Katpudiya Chhina Seraghat MR (Ch-0 to 13 Km) in Bageshwar on date 2018-06-04 15:19:17
31667Subproject Katpudiya Chhina Seraghat MR (Ch-0 to 13 Km) in Bageshwar on date 2018-06-05 08:43:36
31658Subproject Okadi Ana Lohar Chada Gairlekh MR Phase2 (Ch-6 to 12 Km) in Bageshwar on date 2018-06-05 13:01:53
31662Subproject Okadi Ana Lohar Chada Gairlekh MR Phase2 (Ch-6 to 12 Km) in Bageshwar on date 2018-06-05 14:08:26

Random Images

25116
23431
24393
29230
18116
27433
12540
24699
11889

Leave a comment:

Pic Location Map

CAPTCHA code

Data at a Glance

  • Total no. of pics available in system
    31138
  • No. of pics got remarked.
    295
  • Total no. of pics recieved in this month.
    62
  • No. of pics got remarked in this month.
    0
© 2018 ukdisasterrecovery.in