Pic Id: 24747 Uid: 2531
Subproject: Kotkhal jagtoli MR District: Rudraprayag
Data Collector: Mahtab Alam Khan Designation: Site Supervisor
Organisation: DSC1 R&B WB Rudraprayag
Landmark: 5+025 Remark: P.c compaction work
Date: 2016-10-23 12:16:05

Comments:


Yes sir PC and drain work was completed as per specification. And these road was completed on dated 22.04.2017. our staff will pic upload these location next visit 2-3 days of road.
By: Vineet Kumar About Quality
on 28-April-2017 13:03 PM

Ensure PC and drain work as per specification.
By: Ravinder Singh Anand About Quality
on 26-October-2016 13:55 PM


Last Five Images

32488Subproject Birsanikhal-Kota-Silsu-bhutnisi MR in Pauri on date 2018-08-24 13:29:11
32531Subproject Nainipatal Madmaley MR (Ch-7 to 13.162 Km) in Pithoragarh on date 2018-08-30 15:29:55
32535Subproject Kandai Kamoldi Molkakhal MR Phase2 (Ch-0 to 10 Km) in Rudraprayag on date 2018-08-30 16:47:50
32533Subproject Nainipatal Madmaley MR (Ch-7 to 13.162 Km) in Pithoragarh on date 2018-08-30 16:58:29
32577Subproject Bridge at Jokhna Laga Bura in Chamoli on date 2018-09-05 14:59:34

Random Images

29212
25636
29142
24674
24690
24540
25186
31679
30786

Leave a comment:

Pic Location Map

CAPTCHA code

Data at a Glance

  • Total no. of pics available in system
    31530
  • No. of pics got remarked.
    312
  • Total no. of pics recieved in this month.
    108
  • No. of pics got remarked in this month.
    0
© 2018 ukdisasterrecovery.in