Image to be Discussed


24739

Pic Id: 24739 Uid: 1273
Subproject: Sarmola Motor Road District: Chamoli
Data Collector: Pramod Kumar Bhaskar Designation: Site Engineer
Organisation: DSC1 R&B WB Chamoli
Landmark: Ch-0.050 Remark: Laying for pc
Date: 2016-10-23 12:17:10

Comments:


Instruction given to Contractor to ensure PPEs. Contractor agree to ensure complete PPEs in one Week.
By: Ashwini Kumar About Environment
on 19-November-2016 13:31 PM

Site Engineer, Sheladia Associates, please ensure use of PPEs. No labor should be allowed to work without gloves, boots and jackets during laying of PC. Also please place sign boards wherever work is in progress.
By: Ashish Anthwal About Environment
on 24-October-2016 15:10 PM


Last Five Images

32488Subproject Birsanikhal-Kota-Silsu-bhutnisi MR in Pauri on date 2018-08-24 13:29:11
32531Subproject Nainipatal Madmaley MR (Ch-7 to 13.162 Km) in Pithoragarh on date 2018-08-30 15:29:55
32535Subproject Kandai Kamoldi Molkakhal MR Phase2 (Ch-0 to 10 Km) in Rudraprayag on date 2018-08-30 16:47:50
32533Subproject Nainipatal Madmaley MR (Ch-7 to 13.162 Km) in Pithoragarh on date 2018-08-30 16:58:29
32577Subproject Bridge at Jokhna Laga Bura in Chamoli on date 2018-09-05 14:59:34

Random Images

21958
26973
31667
24085
25061
25771
23414
27425
31682

Leave a comment:

Pic Location Map

CAPTCHA code

Data at a Glance

  • Total no. of pics available in system
    31252
  • No. of pics got remarked.
    312
  • Total no. of pics recieved in this month.
    35
  • No. of pics got remarked in this month.
    9
© 2018 ukdisasterrecovery.in