Pic Id: 24611 Uid: 1219
Subproject: Sonla - Kandara - Maikhura Silangi MR District: Chamoli
Data Collector: Ankur Vishwas Designation: Contractor Site Engineer
Organisation: DSC1 R&B WB Chamoli
Landmark: Ch.27. 525 Remark: Kachaa drain work
Date: 2016-10-21 16:11:41

Comments:


All labours are using PPEs at site.Contractor has been informed to place signboards on all the locations where work is in progress.
By: Kirti Vardhan Negi About Social
on 27-January-2017 12:58 PM

DSC and Field PIU, please ensure that no labor work on the site without PPEs. DSC also ensure that sign boards are placed on all the locations where work is in progress
By: Ashish Anthwal About Environment
on 22-October-2016 15:31 PM


Last Five Images

32488Subproject Birsanikhal-Kota-Silsu-bhutnisi MR in Pauri on date 2018-08-24 13:29:11
32531Subproject Nainipatal Madmaley MR (Ch-7 to 13.162 Km) in Pithoragarh on date 2018-08-30 15:29:55
32535Subproject Kandai Kamoldi Molkakhal MR Phase2 (Ch-0 to 10 Km) in Rudraprayag on date 2018-08-30 16:47:50
32533Subproject Nainipatal Madmaley MR (Ch-7 to 13.162 Km) in Pithoragarh on date 2018-08-30 16:58:29
32577Subproject Bridge at Jokhna Laga Bura in Chamoli on date 2018-09-05 14:59:34

Random Images

24569
15718
27426
27552
24639
24187
28973
32879
21101

Leave a comment:

Pic Location Map

CAPTCHA code

Data at a Glance

  • Total no. of pics available in system
    32718
  • No. of pics got remarked.
    312
  • Total no. of pics recieved in this month.
    112
  • No. of pics got remarked in this month.
    0
© 2019 ukdisasterrecovery.in