Pic Id: 24540 Uid: 2652
Subproject: Chaka-Pendarsh Motor raod District: Tehri
Data Collector: Vikas Badoni Designation: Site Supervisor
Organisation: DSC2 R&B WB Tehri
Landmark: 1.600 Remark: Laying of BM
Date: 2016-10-19 16:52:50

Comments:


Contractor representative give me the date 10 november for clear the issues.
By: Vikas Badoni About Others
on 21-October-2016 11:19 AM

Absence of drain and mud heap on khud side are issues in this work.Let us know the plan to rectify it.
By: Er Manoj Bisht About Quality
on 20-October-2016 13:52 PM


Last Five Images

32488Subproject Birsanikhal-Kota-Silsu-bhutnisi MR in Pauri on date 2018-08-24 13:29:11
32531Subproject Nainipatal Madmaley MR (Ch-7 to 13.162 Km) in Pithoragarh on date 2018-08-30 15:29:55
32535Subproject Kandai Kamoldi Molkakhal MR Phase2 (Ch-0 to 10 Km) in Rudraprayag on date 2018-08-30 16:47:50
32533Subproject Nainipatal Madmaley MR (Ch-7 to 13.162 Km) in Pithoragarh on date 2018-08-30 16:58:29
32577Subproject Bridge at Jokhna Laga Bura in Chamoli on date 2018-09-05 14:59:34

Random Images

16137
24524
24775
25522
23872
32466
29141
28935
25265

Leave a comment:

Pic Location Map

CAPTCHA code

Data at a Glance

  • Total no. of pics available in system
    31252
  • No. of pics got remarked.
    312
  • Total no. of pics recieved in this month.
    35
  • No. of pics got remarked in this month.
    9
© 2018 ukdisasterrecovery.in