Image to be Discussed


24105

Pic Id: 24105 Uid: 1106
Subproject: Dyangar-Kathyatbara-Aare bypass MR District: Bageshwar
Data Collector: Mukesh Kumar Yadav 2 Designation: QC
Organisation: DSC5 R&B WB Bageshwar
Landmark: Ch- 3+425 to 3+500 Remark: Stone dust using binding material in WBM G3
Date: 2016-10-09 15:50:37

Comments:


In terms of PPE we can only see Jackets, where are the hard hats and boots? Please ensure complete PPE.
By: Neha Dobhal About Social
on 21-October-2016 15:04 PM

The pattri filling and drain work in progress.
By: Jagdish Narayan Meena About Suggestions
on 18-October-2016 14:55 PM

Good work of WBM.Do the drain and patri filling work before bituminous work.
By: Sunil kumar About Suggestions
on 15-October-2016 16:05 PM


Last Five Images

31664Subproject Katpudiya Chhina Seraghat MR (Ch-0 to 13 Km) in Bageshwar on date 2018-05-31 15:39:00
31666Subproject Katpudiya Chhina Seraghat MR (Ch-0 to 13 Km) in Bageshwar on date 2018-06-04 15:19:17
31667Subproject Katpudiya Chhina Seraghat MR (Ch-0 to 13 Km) in Bageshwar on date 2018-06-05 08:43:36
31658Subproject Okadi Ana Lohar Chada Gairlekh MR Phase2 (Ch-6 to 12 Km) in Bageshwar on date 2018-06-05 13:01:53
31662Subproject Okadi Ana Lohar Chada Gairlekh MR Phase2 (Ch-6 to 12 Km) in Bageshwar on date 2018-06-05 14:08:26

Random Images

21139
15718
24739
25323
23414
28901
24393
27552
18116

Leave a comment:

Pic Location Map

CAPTCHA code

Data at a Glance

  • Total no. of pics available in system
    31038
  • No. of pics got remarked.
    295
  • Total no. of pics recieved in this month.
    51
  • No. of pics got remarked in this month.
    0
© 2018 ukdisasterrecovery.in