Sno. |
District |
Package No. |
Bond/Package Name * |
Contract Start Date |
Agreement Cost |
Cost (in lakhs.) |
Contractor Name |
1st Milestone Date |
2nd Milestone Date |
1st LD Analysis |
2nd LD Analysis |
Amount Retained |
Details |
1. |
Bageshwar |
642
|
UDRP/AF/BR/77 |
01 Dec 2020 |
17,931,582 |
179.32 |
M/s Kundal singh |
05 Nov 2020 |
05 Nov 2020 |
Ld Not applicable |
Calculated LD is Rs 3,335,352 for 372 days |
0.00 |
|
2. |
Nainital |
661
|
UDRP/AF/BR/54 |
01 Dec 2020 |
57,795,934 |
577.96 |
M/s Manu Dev Contractor |
26 Oct 2020 |
26 Oct 2020 |
Ld Not applicable |
Calculated LD is Rs 18,379,128 for 636 days |
0.00 |
|
3. |
Chamoli |
625
|
UDRP/AF/BR/60 |
01 Feb 2020 |
42,080,243 |
420.80 |
M/S.KGL Infrastructure |
22 Jan 2020 |
22 Jan 2020 |
Ld Not applicable |
Calculated LD is Rs 9,089,280 for 432 days |
0.00 |
|
4. |
Uttarkashi |
624
|
UDRP/AF/BR/59 |
01 Feb 2020 |
37,571,581 |
375.72 |
Tons Builderes |
22 Jan 2020 |
22 Jan 2020 |
Ld Not applicable |
Calculated LD is Rs 5,880,018 for 313 days |
0.00 |
|
5. |
Dehradun |
622
|
UDRP/AF/BR/57 |
01 Feb 2020 |
61,746,413 |
617.46 |
M/S.ARKS Universal pvt.ltd |
22 Jan 2020 |
22 Jan 2020 |
Ld Not applicable |
Calculated LD is Rs 13,275,390 for 430 days |
0.00 |
|
6. |
Dehradun |
623
|
UDRP/AF/BR/56 |
01 Feb 2020 |
19,830,912 |
198.31 |
Border Builders |
29 Jul 2020 |
25 Jan 2021 |
Calculated LD is Rs 961,755 for 97 days |
Ld Not applicable |
0.00 |
|
7. |
Tehri |
613
|
UDRP/AF/BR/36 |
01 Feb 2020 |
14,987,873 |
149.88 |
M/S.ARKS Universal pvt.ltd |
22 Jan 2020 |
22 Jan 2020 |
Ld Not applicable |
Calculated LD is Rs 3,477,216 for 464 days |
0.00 |
|
8. |
Pauri |
614
|
UDRP/AF/BR/37 |
01 Feb 2020 |
46,758,700 |
467.59 |
M/S.ARKS Universal pvt.ltd |
22 Jan 2020 |
22 Jan 2020 |
Ld Not applicable |
Calculated LD is Rs 12,998,724 for 556 days |
0.00 |
|
9. |
Dehradun |
615
|
UDRP/AF/BR/38 |
01 Feb 2020 |
20,027,609 |
200.28 |
M/S.ARKS Universal pvt.ltd |
22 Jan 2020 |
22 Jan 2020 |
Ld Not applicable |
Calculated LD is Rs 3,534,942 for 353 days |
0.00 |
|
10. |
Uttarkashi |
648
|
UDRP/AF/BR/81 |
01 Jul 2020 |
51,557,277 |
515.57 |
Border Builders |
10 Jun 2020 |
10 Jun 2020 |
Ld Not applicable |
Calculated LD is Rs 10,827,180 for 420 days |
0.00 |
|
11. |
Uttarkashi |
656
|
UDRP/AF/BR/89 |
01 Jul 2020 |
15,736,964 |
157.37 |
Kailash Hillways Engineering Associates |
30 May 2020 |
30 May 2020 |
Ld Not applicable |
Calculated LD is Rs 3,965,472 for 504 days |
0.00 |
|
12. |
Uttarkashi |
618
|
UDRP/AF/BR/41 |
01 Jul 2020 |
19,940,526 |
199.41 |
Anil Mehta |
30 Nov 2020 |
01 May 2021 |
Calculated LD is Rs 219,340 for 22 days |
Calculated LD is Rs 697,900 for 70 days |
0.00 |
|
13. |
Almora |
659
|
UDRP/AF/BR/92 |
02 Oct 2020 |
83,269,832 |
832.70 |
Gaurav Builder |
10 Jun 2020 |
10 Jun 2020 |
Ld Not applicable |
Calculated LD is Rs 40,760,665 for 979 days |
0.00 |
|
14. |
Tehri |
602
|
UDRP/AF/30(BR) |
03 Aug 2018 |
17,841,142 |
178.41 |
Anil Mehta |
23 Jul 2018 |
23 Jul 2018 |
Ld Not applicable |
Calculated LD is Rs 4,246,396 for 476 days |
0.00 |
|
15. |
Rudraprayag |
701
|
UDRP/AF/SL/05 |
03 Aug 2018 |
176,669,009 |
1,766.69 |
Bharat Construction |
23 Jul 2018 |
23 Jul 2018 |
Ld Not applicable |
Calculated LD is Rs 25,793,820 for 292 days |
0.00 |
|
16. |
Rudraprayag |
702
|
UDRP/AF/SL/06 |
03 Aug 2018 |
138,496,385 |
1,384.96 |
Bharat Construction |
23 Jul 2018 |
23 Jul 2018 |
Ld Not applicable |
Calculated LD is Rs 19,804,928 for 286 days |
0.00 |
|
17. |
Pauri |
650
|
UDRP/AF/BR/83 |
03 Sep 2020 |
94,947,093 |
949.47 |
M/S.ARKS Universal pvt.ltd |
15 Jul 2020 |
15 Jul 2020 |
Ld Not applicable |
Calculated LD is Rs 28,674,296 for 604 days |
0.00 |
|
18. |
Uttarkashi |
658
|
UDRP/AF/BR/91 |
04 Aug 2020 |
27,047,423 |
270.47 |
M/s Harpal singh Kishore singh |
24 Jun 2020 |
24 Jun 2020 |
Ld Not applicable |
Calculated LD is Rs 6,126,372 for 453 days |
0.00 |
|
19. |
Uttarkashi |
657
|
UDRP/AF/BR/90 |
04 Aug 2020 |
20,812,946 |
208.13 |
M/s Harpal singh Kishore singh |
24 Jun 2020 |
24 Jun 2020 |
Ld Not applicable |
Calculated LD is Rs 4,797,166 for 461 days |
0.00 |
|
20. |
Chamoli |
3000
|
UDRP/AF/RBP/02 |
05 Nov 2018 |
123,153,672 |
1,231.54 |
GSCO Infrastructure Pvt Ltd. |
04 May 2019 |
03 Nov 2019 |
Calculated LD is Rs 17,426,291 for 283 days |
Calculated LD is Rs 25,308,147 for 411 days |
0.00 |
|
21. |
Chamoli |
3001
|
UDRP/AF/RBP/04 |
05 Nov 2018 |
173,171,085 |
1,731.71 |
Bharat Construction |
25 Oct 2018 |
25 Oct 2018 |
Ld Not applicable |
Calculated LD is Rs 59,571,168 for 688 days |
0.00 |
|
22. |
Tehri |
3002
|
UDRP/AF/RBP/05 |
05 Nov 2018 |
222,747,269 |
2,227.47 |
Bharat Construction |
25 Oct 2018 |
25 Oct 2018 |
Ld Not applicable |
Calculated LD is Rs 55,464,252 for 498 days |
0.00 |
|
23. |
Almora |
603
|
UDRP/AF/31(BR) |
05 Oct 2018 |
16,477,350 |
164.77 |
Maa Shailputri Associates |
28 Sep 2018 |
28 Sep 2018 |
Ld Not applicable |
Calculated LD is Rs 2,685,914 for 326 days |
0.00 |
|
24. |
Almora |
666
|
UDRP/AF/BR/85 |
06 Feb 2021 |
49,143,534 |
491.44 |
M/s Manu Dev Contractor |
19 Jan 2021 |
19 Jan 2021 |
Ld Not applicable |
Calculated LD is Rs 15,996,372 for 651 days |
0.00 |
|
25. |
Uttarkashi |
630
|
UDRP/AF/BR/69 |
06 Feb 2021 |
54,397,225 |
543.97 |
M/s. Valley Construction Company Pvt.Ltd. |
18 Jan 2021 |
18 Jan 2021 |
Ld Not applicable |
Calculated LD is Rs 21,677,603 for +797 days |
0.00 |
|
26. |
Uttarkashi |
644
|
UDRP/AF/BR/79 |
06 Nov 2020 |
16,727,986 |
167.28 |
M/S Utsav Associate |
24 Jun 2021 |
08 Feb 2022 |
Calculated LD is Rs 1,154,232 for 138 days |
Calculated LD is Rs 2,325,192 for 278 days |
0.00 |
|
27. |
Almora |
604
|
UDRP/AF/32(BR) |
07 Dec 2018 |
134,280,079 |
1,342.80 |
Kailash Hillways Engineering Associates |
29 Nov 2018 |
29 Nov 2018 |
Ld Not applicable |
Calculated LD is Rs 49,280,760 for 734 days |
0.00 |
|
28. |
Uttarkashi |
605
|
UDRP/AF/33(BR) |
07 Jul 2018 |
49,492,438 |
494.92 |
Kailash Hillways Engineering Associates |
29 Jun 2018 |
29 Jun 2018 |
Ld Not applicable |
Calculated LD is Rs 11,556,382 for 467 days |
0.00 |
|
29. |
Chamoli |
652
|
UDRP/AF/BR/73 |
08 Jan 2021 |
30,982,577 |
309.83 |
Anil Mehta |
23 Dec 2020 |
23 Dec 2020 |
Ld Not applicable |
Calculated LD is Rs 6,769,567 for 437 days |
0.00 |
|
30. |
Uttarkashi |
655
|
UDRP/AF/BR/58 |
08 Jan 2021 |
89,909,595 |
899.10 |
Kailash Hillways Engineering Associates |
19 Sep 2021 |
01 Jun 2022 |
Calculated LD is Rs 1,753,245 for 39 days |
Ld Not applicable |
0.00 |
|
31. |
Nainital |
663
|
UDRP/AF/BR/98 |
09 Dec 2020 |
62,091,337 |
620.91 |
HMR Construction Pvt. Ltd. |
20 Oct 2020 |
20 Oct 2020 |
Ld Not applicable |
Calculated LD is Rs 14,715,804 for 474 days |
0.00 |
|
32. |
Tehri |
709
|
UDRP/AF/SL/12 |
09 Jul 2020 |
54,390,157 |
543.90 |
Global Construction |
02 Jun 2020 |
02 Jun 2020 |
Ld Not applicable |
Calculated LD is Rs 7,152,285 for 263 days |
0.00 |
|
33. |
Pithoragarh |
640
|
UDRP/AF/BR/78 |
09 Jul 2020 |
52,547,593 |
525.48 |
M/S Aggarwal Brothers |
23 May 2020 |
23 May 2020 |
Ld Not applicable |
Calculated LD is Rs 18,812,184 for 716 days |
0.00 |
|
34. |
Pauri |
635
|
UDRP/AF/BR/51 |
09 Sep 2020 |
58,111,372 |
581.11 |
Gaurav Builder |
24 Aug 2020 |
24 Aug 2020 |
Ld Not applicable |
Calculated LD is Rs 15,254,400 for 525 days |
0.00 |
|
35. |
Bageshwar |
641
|
UDRP/AF/BR/62 |
10 Dec 2020 |
70,802,433 |
708.02 |
M/s Hillways Construction Company Pvt. Ltd. |
12 Nov 2020 |
12 Nov 2020 |
Ld Not applicable |
Calculated LD is Rs 9,593,671 for 271 days |
0.00 |
|
36. |
Bageshwar |
633
|
UDRP/AF/BR/42 |
10 Jul 2020 |
78,090,725 |
780.91 |
M. S. Associates |
24 Jun 2020 |
24 Jun 2020 |
Calculated LD is Rs 28,541,895 for 731 days |
Calculated LD is Rs 28,541,895 for 731 days |
0.00 |
|
37. |
Rudraprayag |
636
|
UDRP/AF/BR/45 |
10 Nov 2020 |
28,562,466 |
285.62 |
M/s Harpal singh Kishore singh |
16 Oct 2020 |
16 Oct 2020 |
Ld Not applicable |
Calculated LD is Rs 5,812,367 for 407 days |
0.00 |
|
38. |
Almora |
637
|
UDRP/AF/BR/94 |
10 Sep 2020 |
65,956,235 |
659.56 |
Gaurav Builder |
10 Jun 2020 |
10 Jun 2020 |
Ld Not applicable |
Calculated LD is Rs 28,525,970 for 865 days |
0.00 |
|
39. |
Nainital |
645
|
UDRP/AF/BR/65 |
10 Sep 2020 |
20,663,226 |
206.63 |
Gaurav Builder |
24 Jun 2020 |
24 Jun 2020 |
Ld Not applicable |
Calculated LD is Rs 3,151,260 for 305 days |
0.00 |
|
40. |
Tehri |
606
|
UDRP/AF/29(BR) |
12 Jul 2018 |
85,440,258 |
854.40 |
Kailash Hillways Engineering Associates |
02 Jul 2018 |
02 Jul 2018 |
Ld Not applicable |
Calculated LD is Rs 37,123,680 for 869 days |
0.00 |
|
41. |
Almora |
646
|
UDRP/AF/BR/88 |
13 Dec 2020 |
119,142,240 |
1,191.42 |
V. K. Gupta & Associates |
02 Dec 2020 |
02 Dec 2020 |
Ld Not applicable |
Calculated LD is Rs 31,632,201 for 531 days |
0.00 |
|
42. |
Pithoragarh |
667
|
UDRP/AF/BR/52 |
13 Feb 2021 |
101,220,222 |
1,012.20 |
M/s Hillways Construction Company Pvt. Ltd. |
29 Jan 2021 |
29 Jan 2021 |
Ld Not applicable |
Calculated LD is Rs 16,093,980 for 318 days |
0.00 |
|
43. |
Tehri |
706
|
UDRP/AF/SL/09 |
13 Jul 2020 |
37,759,210 |
377.59 |
Global Construction |
19 Jun 2020 |
19 Jun 2020 |
Ld Not applicable |
Calculated LD is Rs 4,342,400 for 230 days |
0.00 |
|
44. |
Nainital |
653
|
UDRP/AF/BR/86 |
13 Nov 2020 |
138,294,240 |
1,382.94 |
V. K. Gupta & Associates |
06 Oct 2020 |
06 Oct 2020 |
Ld Not applicable |
Calculated LD is Rs 31,047,003 for 449 days |
0.00 |
|
45. |
Nainital |
662
|
UDRP/AF/BR/99 |
14 Nov 2020 |
66,754,174 |
667.54 |
M/S.KGL Infrastructure |
26 Oct 2020 |
26 Oct 2020 |
Ld Not applicable |
Calculated LD is Rs 15,787,321 for 473 days |
0.00 |
|
46. |
Uttarkashi |
631
|
UDRP/AF/BR/64 |
15 Feb 2020 |
49,381,334 |
493.81 |
Tons Builderes |
07 Feb 2020 |
07 Feb 2020 |
Ld Not applicable |
Calculated LD is Rs 9,209,743 for 373 days |
0.00 |
|
47. |
Tehri |
707
|
UDRP/AF/SL/10 |
15 Feb 2020 |
22,590,175 |
225.90 |
M/S JaiKedar construction company |
07 Feb 2020 |
07 Feb 2020 |
Ld Not applicable |
Calculated LD is Rs 4,269,510 for 378 days |
0.00 |
|
48. |
Tehri |
705
|
UDRP/AF/SL/08 |
15 Feb 2020 |
47,858,029 |
478.58 |
M/S Garware Technical fibers Ltd. |
07 Feb 2020 |
07 Feb 2020 |
Ld Not applicable |
Calculated LD is Rs 9,739,103 for 407 days |
0.00 |
|
49. |
Uttarkashi |
639
|
UDRP/AF/BR/72 |
15 Feb 2020 |
54,743,129 |
547.43 |
Kailash Hillways Engineering Associates |
07 Feb 2020 |
07 Feb 2020 |
Ld Not applicable |
Calculated LD is Rs 19,488,864 for 712 days |
0.00 |
|
50. |
Bageshwar |
617
|
UDRP/AF/BR/40 |
15 Feb 2020 |
28,163,186 |
281.63 |
M/S.KGL Infrastructure |
07 Feb 2020 |
07 Feb 2020 |
Ld Not applicable |
Calculated LD is Rs 6,167,916 for 438 days |
0.00 |
|
51. |
Udham Singh Nagar |
608
|
UDRP/AF/35(BR) |
15 Jun 2019 |
94,827,516 |
948.28 |
Doon Infrastructure Ltd. |
03 Jun 2019 |
03 Jun 2019 |
Ld Not applicable |
Calculated LD is Rs 29,538,922 for 623 days |
0.00 |
|
52. |
Uttarkashi |
607
|
UDRP/AF/34(BR) |
16 Dec 2019 |
17,142,785 |
171.43 |
M/S Utsav Associate |
16 Apr 2020 |
15 Aug 2020 |
Calculated LD is Rs 462,834 for 54 days |
Calculated LD is Rs 2,511,303 for 293 days |
0.00 |
|
53. |
Almora |
651
|
UDRP/AF/BR/84 |
16 Oct 2020 |
25,904,638 |
259.05 |
Gaurav Builder |
06 Jul 2020 |
06 Jul 2020 |
Ld Not applicable |
Calculated LD is Rs 11,423,664 for 882 days |
0.00 |
|
54. |
Almora |
654
|
UDRP/AF/BR/87 |
19 Dec 2020 |
119,108,640 |
1,191.09 |
V. K. Gupta & Associates |
10 Dec 2020 |
10 Dec 2020 |
Ld Not applicable |
Calculated LD is Rs 25,846,436 for 434 days |
0.00 |
|
55. |
Tehri |
632
|
UDRP/AF/BR/63 |
20 Feb 2020 |
20,571,233 |
205.71 |
M/S Beer Chandra Ramola |
12 Feb 2020 |
12 Feb 2020 |
Ld Not applicable |
Calculated LD is Rs 4,278,976 for 416 days |
0.00 |
|
56. |
Champawat |
610
|
UDRP/AF/BR/96 |
21 Aug 2020 |
25,133,492 |
251.33 |
M/s Laxmi Datt Binwal |
14 Jul 2020 |
14 Jul 2020 |
Ld Not applicable |
Calculated LD is Rs 6,094,995 for 485 days |
0.00 |
|
57. |
Tehri |
634
|
UDRP/AF/SL/11 |
21 Aug 2020 |
48,969,123 |
489.69 |
M/S Garware Technical fibers Ltd. |
29 Jun 2020 |
29 Jun 2020 |
Ld Not applicable |
Calculated LD is Rs 13,123,960 for 536 days |
0.00 |
|
58. |
Pithoragarh |
626
|
UDRP/AF/BR/46 |
21 Aug 2020 |
103,819,070 |
1,038.19 |
M/s Laxmi Datt Binwal |
14 Jul 2020 |
14 Jul 2020 |
Ld Not applicable |
Calculated LD is Rs 22,477,030 for 433 days |
0.00 |
|
59. |
Uttarkashi |
647
|
UDRP/AF/BR/80 |
21 Aug 2020 |
55,121,698 |
551.22 |
Tons Builderes |
14 Jul 2020 |
14 Jul 2020 |
Ld Not applicable |
Calculated LD is Rs 11,630,742 for 422 days |
0.00 |
|
60. |
Rudraprayag |
3003
|
UDRP/AF/RBP/07 |
21 Jan 2020 |
61,098,635 |
610.99 |
Chaudhary Sandeep Contractor & Suppliers |
14 Jan 2020 |
14 Jan 2020 |
Ld Not applicable |
Calculated LD is Rs 21,414,849 for 701 days |
0.00 |
|
61. |
Uttarkashi |
649
|
UDRP/AF/BR/82 |
21 Nov 2020 |
12,316,117 |
123.16 |
M/S Utsav Associate |
05 Nov 2020 |
05 Nov 2020 |
Ld Not applicable |
Calculated LD is Rs 2,752,626 for 447 days |
0.00 |
|
62. |
Nainital |
704
|
UDRP/AF/SL/07 |
25 Nov 2021 |
41,863,273 |
418.63 |
M/s Stonefield Construction |
28 Oct 2021 |
28 Oct 2021 |
Ld Not applicable |
Calculated LD is Rs 5,944,688 for 284 days |
0.00 |
|
63. |
Almora |
660
|
UDRP/AF/BR/93 |
27 Aug 2020 |
46,814,331 |
468.14 |
Gaurav Builder |
06 Jul 2020 |
06 Jul 2020 |
Ld Not applicable |
Calculated LD is Rs 11,867,349 for 507 days |
0.00 |
|
64. |
Bageshwar |
616
|
UDRP/AF/BR/39 |
27 Jan 2020 |
39,760,202 |
397.60 |
M/S.Dalip Singh Adhikari |
20 Jan 2020 |
20 Jan 2020 |
Ld Not applicable |
Calculated LD is Rs 10,337,600 for 520 days |
0.00 |
|
65. |
Bageshwar |
619
|
UDRP/AF/44(BR) |
27 Jan 2020 |
33,208,175 |
332.08 |
M/S.Dalip Singh Adhikari |
20 Jan 2020 |
20 Jan 2020 |
Ld Not applicable |
Calculated LD is Rs 12,037,900 for 725 days |
0.00 |
|
66. |
Pithoragarh |
620
|
UDRP/AF/BR/47 |
27 Jan 2020 |
86,310,066 |
863.10 |
M/S.G.S.Matiyani and sons |
20 Jan 2020 |
20 Jan 2020 |
Ld Not applicable |
Calculated LD is Rs 25,893,000 for 600 days |
0.00 |
|
67. |
Bageshwar |
621
|
UDRP/AF/BR/61 |
27 Jan 2020 |
19,025,698 |
190.26 |
M/S.Dalip Singh Adhikari |
20 Jan 2020 |
20 Jan 2020 |
Ld Not applicable |
Calculated LD is Rs 5,603,157 for 589 days |
0.00 |
|
68. |
Nainital |
664
|
UDRP/AF/BR/100 |
28 Nov 2020 |
109,437,900 |
1,094.38 |
M/S.KGL Infrastructure |
|
|
Ld Not applicable |
Ld Not applicable |
0.00 |
|
69. |
Tehri |
628
|
UDRP/AF/BR/55 |
28 Oct 2020 |
63,617,925 |
636.18 |
Triveni Construction Company |
12 Oct 2020 |
12 Oct 2020 |
Ld Not applicable |
Calculated LD is Rs 8,620,239 for 271 days |
0.00 |
|
70. |
Chamoli |
3004
|
UDRP/AF/RBP/08 |
29 Jan 2020 |
107,897,353 |
1,078.97 |
M/S Ajay kumar contractor |
22 Jan 2020 |
22 Jan 2020 |
Ld Not applicable |
Calculated LD is Rs 27,513,990 for 510 days |
0.00 |
|
71. |
Nainital |
643
|
UDRP/AF/BR/75 |
29 Oct 2020 |
57,926,186 |
579.26 |
M/S.KGL Infrastructure |
15 Sep 2020 |
15 Sep 2020 |
Ld Not applicable |
Calculated LD is Rs 11,411,422 for 394 days |
0.00 |
|
72. |
Pauri |
665
|
UDRP/AF/BR/66 |
29 Oct 2020 |
184,550,240 |
1,845.50 |
V. K. Gupta & Associates |
06 Oct 2020 |
06 Oct 2020 |
Ld Not applicable |
Calculated LD is Rs 47,337,075 for 513 days |
0.00 |
|
73. |
Rudraprayag |
703
|
UDRP/AF/SL/03 |
30 Sep 2018 |
34,906,911 |
349.07 |
Starcon Infra Projects (I) Pvt. Ltd. |
25 Sep 2018 |
25 Sep 2018 |
Calculated LD is Rs 23,893,157 for 1369 days |
Calculated LD is Rs 23,893,157 for 1369 days |
0.00 |
|
|
Total Cost |
4,577,425,203.63 |
45,774.22 |
|
|
|
0.00 |
1,124,314,239.00 |
0.00 |
|