MIS Dashboard

PIU Bridge,Slope & Irrigation
PIU Public Building
Total Cost
Particulars Bridges (in No) Bridges Cost (in Crore) Slope (in No) Slope Cost (in Crore) RBP (in No) RBP Cost (in Crore) Public Building (Building in No) Public Building Cost (in Crore) Total Cost (in Crore)
Approved by HPC (no of Subproject)
58
337.39
8
64.36
5
82.37
3
161.93
646.05
Agreement signed (no of Packages)
58
330.58
8
63.93
5
68.63
3
159.98
623.12
   
   

Work Progress

Particular Bridges Slopes Irrigation Public Building
Physical Progress Graph(in %)
91.44%
92.35%
96.84%
41.33%
Expenditure Graph (in %) 
92.92%
88.55%
97.32%
65.58%
Expenditure (in Lacs) 
31443.68
5970.55
6679.29
10896.18
Completed Subproject
30
7
2
0
   
   

Process Updated on Date and Duration after last update

Particular Bridges/Slopes Irrigation
Date Days Date Days
Package Updation
28-October-21 706 22-January-20 1351
Subproject Progress
(financial)
03-October-23 1 06-June-22 485
Subproject Progress
(Physical)
Not Done Any entry 0 Not Done Any entry 0
Bond Bank Security Info 31-May-22 491 02-March-22 581
Consultancy Updation 19-December-18 1750 13-October-18 1817

Activities done in no.(Planning Phase)

Particulars Bridges/Slopes Irrigation
Yes No Yes No
Maps
75 9 6 0
Photo Gallery
69 15 5 1
Bond Info
entry Status
72 0 6 0

Real Time Pics Collection