Urban Water Supply

Disaster in the month of June 2013 caused extensive damage to infrastructure facilities in Uttarakhand, as a measure to restore and rehabilitate the damaged infrastructure components Uttarakhand Jal Sansthan under Uttarakhand Emergency Assistance Project through the assistance from ADB Aimed to rehabilitate and reconstruct damaged water supply schemes in 9 urban towns of the state of Uttarakhand namely Kapkot, Bageshwar, Dharchula, Rudraprayag, Karanprayag, Gauchar, Uttarakashi, Devprayag, Srinagar-Pauri.
 
The works of rehabilitation included replacement of damaged pipeline, construction of storage reservoirs, pumping plants and Automation systems. In addition to above as a first step towards modernisation of water supply schemes Automatic Water Metering system as pilot Project was undertaken in Srinagar town of Uttarakhand. Under the project in urban water supply sector works in 9 towns were implemented through 12 contract packages. M/S STUP Consultants were involved as Design and Supervision Agency for the above Projects. The total Sanctioned/Completed cost of the Project is INR 87.33Cr. and total disbursements till date is INR 82.32Cr. Physical Works in All the 12 work packages have been completed and financial closure of 10 Projects completed. Brief about each contract package is as given below:
 
  • Kapkot Water Supply Scheme Work CompletedRBF well - 1nos,  Pipe line work - 7348m

  • Bageshwar Water Supply Scheme Work CompletedPipe line work 1091m, BF wall- 1nos, Alum Godown- 1 nos, Rehabilitation of WTP Thakurdwara

  • Dharchula Water Supply Scheme Work Completed - Construction of 25KL, 50KL & 300KL GSLR, RCC intake chamber works, Uttaranchal Koop installation, HFRF Work, Pipe line work 8234m.

  • Rudraprayag Water Supply Scheme Work CompletedUttaranchal Koop Installation 3nos, Pipe line work 5880m., Office building 1nos, Stream Crossing 2nos

  • Karanprayag Water Supply Scheme Work Completed - Office Building 1 nos, Pipe line work 14023m, RBF Well 1nos, Construction of 500 KL, 150KL, 35 KL GLSR work, Construction of 100KL SUMP and Pump house

  • Gauchar Water Supply Scheme Work Completed - Construction of Office Building 1 nos, 100KL GLSR work 1 nos, 100KL SUMP and Pump house 1 nos, Pipes line work 11126m., Infiltration Well – completed., Panel room & Boundary wall completed.,

  • Uttarkashi Water Supply Scheme Work Completed - Construction of Tube well 2 Nos., Pipe line work 5967m., Water Treatment Plant – Rehabilitation works at Bhattwadi & Gufiyara., Protection wall work at Gufiyara WTP

  • Devprayag Water Supply Scheme Work Completed -Construction of Office building- 1nos, Boundary wall works of Office building & 50KL GLSR, Installation of 3 nos Uttaranchal Koop, Pipe Line Work- 31331m, 50Kl GLSR

  • Srinagar/Pauri Water Supply Scheme Work Completed - Pump house at RBF, Pipeline Works-31314m., Construction of Office building – 1nos, 1000KL GLSR – 1nos, 500KL SUMP- 1nos, SCADA room, 200 KL GLSR -1nos, Rehabilitation of WTP work

  • Srinagar (Tube well) work completed - Construction of Tube Wells, Monitoring & development- 6nos, Boundary wall & chain link fencing works, Fencing around the Tubewells, RBF site path way work

  • Srinagar (AMR) work completed – - 5676 meters installed of 15mm to 150mm., Pipeline Works-8100m.

  • Kapkot (Additional work) work completed – - Pipe line works- 7880m., Construction of 200KL GLSR - 2nos

 
Document Downloads                   

Links of UEAP