  • HPC sanctioned 92 Packages consisting of 110 roads of length 1968 Km amounting to INR 863.97 Cr.
  • Agreement and work orders for 92 Packages comprising of 110 roads of length 1968 km worth INR 771.78 Cr have been awarded and completed.
  • Quantum of work completed :
  1. SDBC- 1199 km
  2. Causeway- 431 nos
  3. RCC Slab/Scupper/culvert- 550 nos
  4. Drain- 1155 km
  5. Crash barrier -141 km
  • 85 Works have been completed till date and thus the Physical progress is 100%.

   

  • HPC sanctioned 12 packages, Contract Awarded INR 86.38 Cr.
  • The works of rehabilitation included replacement of damaged pipeline, construction of storage reservoirs, pumping plants and Automation systems. In addition to above as a first step towards modernisation of water supply schemes Automatic Water Metering system as pilot Project was undertaken in Srinagar town of Uttarakhand. Under the project in urban water supply sector total works in 9 towns were implemented through 12 contract packages. M/S STUP Consultants were involved as Design and Supervision Agency for the above Projects. The total Sanctioned/Completed cost of the Project is INR 87.33Cr. and total disbursements till date is INR 82.32Cr. Physical Works in All the 12 work packages have been completed and financial closure of 10 Projects completed.

GMVN

  • HPC sanctioned 04 packages contract awarded worth  INR 37.21Cr. 
  • Construction of FRP and Hybrid Huts in Uttarkashi, Garhwal Region(1) Purola – Foundation work up to Plinth has been completed. The work of retaining wall is in progress. Hybrid hut material manufactured at factory is to be transported to site. (2) Barkot – PCC work in Column footing has been completed. Column Footing work is in progress. (3) Phoolchatti – Foundation work up to Plinth has been completed in 1st Block. Excavation & PCC work in foundation of column footing in 2nd Block is in progress. (4) Raithal – Foundation work up to plinth level has been completed in Ist hut. R.C.C work in plinth bend has been completed and earth filling work is in progress in 2nd hut. Hill cutting work has been completed. (5) Barsu – Retaining wall in progress foundation work of 5 Huts upto plinth level completed. (6) Harsil – Foundation work up to plinth level has been completed in Ist hut. 2nd hut shifted to Barsu. Site planning for one additional hut at Barsu is in progress. Hybrid hut material manufactured at factory is to be transported to site.

  • Construction of Hybrid Huts in Rudraprayag, Garhwal Region.(1) Kanakchauri - Hill cutting work, PCC work in column footing of 1st Block has been completed and RCC work in column footing is in progress.
  • Construction of Hybrid Huts in Chamoli, Garhwal Region.(1) Pandukeshwar - Foundation work progress in 2 Huts. (2) Auli – PCC in foundation in column footing have been completed RCC work in colomn is in progress in both the sites. (3) Joshimath- Civil work has been completed Erection will start from 10 Sep’15. (4) Deval – Civil wok has been completed and plaster work in plinth is in progress. (5) Lohjung –RCC work of Plinth Beam is in progress.

  • Construction/Reconstruction of Tourism Assets in LGFS Structure in Various Locations at Rudraprayag District, Garhwal Region.(1)Tilwara- Foundation up to plinth has been completed in 10 No. huts & RCC work in column footing work is in progress in 3 Nos huts. Erection of LGFS Structure for 2 huts have been completed. (2)Jakholi - Foundation work upto plinth level has been completed. LGFS hut material manufactured at factory is to be transported to site.(3)Guptkashi- Hill cutting work completed & RCC work in retaining wall has been completed. Excavation of foundation work is completed.(4)Triyuginarayan- RCC works of platform for 03 Huts completed and work in progress in 01 Huts. RR stone masonry work in retaining wall in progress.(5)Gaurikund- RCC work in column footing is in progress. (6)Sonprayag- Base Architectural drawing have been approved and sent to contractor for submission of structural drawing. Site development work is in progress.

  • Rehabilitation & Restoration of Tourist Rest Houses in Various Locations at Rudraprayag District, Garhwal Region The Package has been split into 6 lots after obtaining approval from ADB. The NIT for these lots has been invited on 16.09.2015. Deadline for submission of bids are 15.10.2015.

KMVN

  • HPC sanctioned 02 packages(pithoragarh & Bageshwar) contract awareded worth INR 26.68 Cr. 
  • Construction of FRP Huts in Pithoragarh District. & samecontsructruction of FRP & Hybrid Huts in Bageshwar District.
  • (Helipads/Heliports): Helipad sites under 27 Helipad sites work under process. 

  • Jollygrant :Work started. Tyuni : NTP issued. Work to be started. Daschula : Excavation completed. Jageshwar : Excavation completed. Munsiyari : NTP issued. Work to be started. Almora Police Line: GSB work in progress. Yamkeshwar : Earthwork complete in FATO. GSB to be start. Sahastradhara : DLC completed. Bageshwar P.G. College : Excavation completed. Chaukodi : Excavation work in progress. Petshal : Work to be started. Sosa : DLC completed. Banbasa : DLC completed. Kashipur : Excavation completed. Garud : Excavation Completed. Kotdwar : DLC completed. Mori : Excavation completed. Barkot: Excavation completed. Khati : Excavation completed. Kapkot : PQC completed. Chaukhutia : PQC completed. Dwarahat : PQC completed. Champawat : Excavation completed. GSB laying partialy done. Augastyamuni: PQC completed. Auli : DLC completed. Narendra Nagar : PQC completed. Chamba : PQC completed.

  • Equipment: Quotation has been cancelled due to no-responsive firms.
  • Hanger: NTP issued for 04 Hangar (Sahastradhara, Gaucha, Naini-Saini, Chinyalisuar). Work started at Sahastradhara. Work to be started at 03 Hangars.

              

 

·        