UEAP

          Roads and Bridges  Urban Water Supply 

Tourism 

             Civil Aviation 
  • HPC sanctioned 92 Packages consisting of 110 roads of length 1968 Km amounting to INR 861.78 Cr.
  • Agreement and work orders for 92 Packages comprising of 110 roads of length 1968 km worth INR 782.57 Cr have been awarded till now. Works of 92 roads of Length 1968 km amounting to INR 782.57 Cr is under progress.
  • Quantum of work completed :
  1. SDBC- 1176 km
  2. Causeway- 412 nos
  3. RCC Slab/Scupper/culvert- 522 nos
  4. Drain- 1131 km
  5. Crash barrier -141 km
  • 85 Works have been completed till date and thus the Physical progress is 96%.

   

  • HPC sanctioned 12 packages, Contract Awarded INR 86.38 Cr.
  • Kapkot Water Supply Scheme – Infiltration well – Completed. Pipes line laying, Jointing and Hydro testing completed. (7641m), Hand over – 07-04-2017.

    • Bageshwar Water Supply Scheme-  Pipes line laying, Jointing & Hydro testing completed. (1176m), Pumps 4 nos -Two pumps commissioned at Kathayatbada clear water pump and two pumps commissioned at RWPH Kathayatbada, Infiltration wall- Completed, Alum Godown- Completed. Rehabilitation of WTP Thakurdwara - Completed.

    • Dharchula Water Supply Scheme - Construction of 25KL, 50KL & 300KL GSLR, RCC intake chamber work completed. Uttaranchal Koop installation completed. HFRF - Work completed. Pipes line laying, Jointing & Hydro testing completed. (7958m). Hand over – 01-06-2017.

     • Rudraprayag Water Supply Scheme  – 3nos Uttaranchal Koop Installation completed. Laying, jointing & hydraulic testing completed- 5880m. Office building- completed. Stream Crossing- completed. Hand over -  25-04-2017.

    • Karanprayag Water Supply Scheme  - Office Building - Completed. Pipe line work -13860m Laid. 10221m hydro testing done. Infiltration Well–Civil work completed. Commissioning of pumps (2 sub, 2 Centrifugal) completed. 500 KL, 150KL, 35 KL GLSR hydro testing done. 100KL SUMP and Pump house completed. DG set & SCADA panel room finishing work completed. Hand over -  31-05-2017 .

    • Gauchar Water Supply Scheme –   

    Office Building- Completed. 100KL GLSR work completed. 100KL SUMP and Pump house completed. Laying, jointing & hydraulic testing completed of Gravity pipeline -11120m. Infiltration Well–Civil work completed. Panel room & Boundary wall completed. Extra Items – Approach road of Pump house & Boundary wall work completed. Boundary wall of 100Kl GLSR. RCC retaining wall work completed. Hand over -  31-05-2017

    • Uttarkashi Water Supply Scheme

    Construction of Tube well – 2 Nos completed. Laying, jointing & hydraulic testing completed of Gravity pipeline -5967m. Water Treatment Plant – Completed at Bhattwadi  & Gufiyara. Protection wall work 2nd phase work in progress at Gufiyara WTP. Pump house - Completed.

    • Devprayag Water Supply Scheme

    Office building inauguration on 20.12.2016. Extra Items- Boundary wall work completed of Office building & 50KL GLSR site. Installation of 3 nos Uttaranchal Koop completed. Pipe Line Work- Laying , Jointing & tasting 31370m done. 50Kl GLSR completed. Hand over -  01-06-2017

    • Srinagar/Pauri Water Supply Scheme

    Pump house civil completed at RBF. Installation, commissioning & trial run of 34 Pumps completed. Pipeline Works-31314m laid and 27015m hydraulic testing done. Office Building-Completed. 1000KL GLSR - Completed. 500KL SUMP- Completed. SCADA room- Completed.200 KL GLSR –Completed. Rehabilitation of WTP work completed.

  • UK/UEAP-WSS-GW/02-1 Srinagar- 

    Srinagar (Tube well) - Construction of Tube Wells. All 06 nos tubewells monitoring done. All 06 nos tubewells development completed. Boundary wall & chain link fencing Completed. Fencing around the Tubewell completed. RBF site path way work completed. Hand over - 07-06-2017.

  • Srinagar-AMR Water Meter- 

    732 meters installed of 15mm.

  • Kapkot (Additional work GLSR and Distribution Network)- 

    Pipe line laying - 150m. 200KL GLSR – Excavation is in progress.

GMVN

  • HPC sanctioned 04 packages contract awarded worth  INR 37.21Cr. 
  • Construction of FRP and Hybrid Huts in Uttarkashi, Garhwal Region(1) Purola – Foundation work up to Plinth has been completed. The work of retaining wall is in progress. Hybrid hut material manufactured at factory is to be transported to site. (2) Barkot – PCC work in Column footing has been completed. Column Footing work is in progress. (3) Phoolchatti – Foundation work up to Plinth has been completed in 1st Block. Excavation & PCC work in foundation of column footing in 2nd Block is in progress. (4) Raithal – Foundation work up to plinth level has been completed in Ist hut. R.C.C work in plinth bend has been completed and earth filling work is in progress in 2nd hut. Hill cutting work has been completed. (5) Barsu – Retaining wall in progress foundation work of 5 Huts upto plinth level completed. (6) Harsil – Foundation work up to plinth level has been completed in Ist hut. 2nd hut shifted to Barsu. Site planning for one additional hut at Barsu is in progress. Hybrid hut material manufactured at factory is to be transported to site.

  • Construction of Hybrid Huts in Rudraprayag, Garhwal Region.(1) Kanakchauri - Hill cutting work, PCC work in column footing of 1st Block has been completed and RCC work in column footing is in progress.
  • Construction of Hybrid Huts in Chamoli, Garhwal Region.(1) Pandukeshwar - Foundation work progress in 2 Huts. (2) Auli – PCC in foundation in column footing have been completed RCC work in colomn is in progress in both the sites. (3) Joshimath- Civil work has been completed Erection will start from 10 Sep’15. (4) Deval – Civil wok has been completed and plaster work in plinth is in progress. (5) Lohjung –RCC work of Plinth Beam is in progress.

  • Construction/Reconstruction of Tourism Assets in LGFS Structure in Various Locations at Rudraprayag District, Garhwal Region.(1)Tilwara- Foundation up to plinth has been completed in 10 No. huts & RCC work in column footing work is in progress in 3 Nos huts. Erection of LGFS Structure for 2 huts have been completed. (2)Jakholi - Foundation work upto plinth level has been completed. LGFS hut material manufactured at factory is to be transported to site.(3)Guptkashi- Hill cutting work completed & RCC work in retaining wall has been completed. Excavation of foundation work is completed.(4)Triyuginarayan- RCC works of platform for 03 Huts completed and work in progress in 01 Huts. RR stone masonry work in retaining wall in progress.(5)Gaurikund- RCC work in column footing is in progress. (6)Sonprayag- Base Architectural drawing have been approved and sent to contractor for submission of structural drawing. Site development work is in progress.

  • Rehabilitation & Restoration of Tourist Rest Houses in Various Locations at Rudraprayag District, Garhwal Region The Package has been split into 6 lots after obtaining approval from ADB. The NIT for these lots has been invited on 16.09.2015. Deadline for submission of bids are 15.10.2015.

KMVN

  • HPC sanctioned 02 packages(pithoragarh & Bageshwar) contract awareded worth INR 26.68 Cr. 
  • Construction of FRP Huts in Pithoragarh District. & samecontsructruction of FRP & Hybrid Huts in Bageshwar District.
  • (Helipads/Heliports): Helipad sites under 27 Helipad sites work under process. 

  • Jollygrant :Work started. Tyuni : NTP issued. Work to be started. Daschula : Excavation completed. Jageshwar : Excavation completed. Munsiyari : NTP issued. Work to be started. Almora Police Line: GSB work in progress. Yamkeshwar : Earthwork complete in FATO. GSB to be start. Sahastradhara : DLC completed. Bageshwar P.G. College : Excavation completed. Chaukodi : Excavation work in progress. Petshal : Work to be started. Sosa : DLC completed. Banbasa : DLC completed. Kashipur : Excavation completed. Garud : Excavation Completed. Kotdwar : DLC completed. Mori : Excavation completed. Barkot: Excavation completed. Khati : Excavation completed. Kapkot : PQC completed. Chaukhutia : PQC completed. Dwarahat : PQC completed. Champawat : Excavation completed. GSB laying partialy done. Augastyamuni: PQC completed. Auli : DLC completed. Narendra Nagar : PQC completed. Chamba : PQC completed.

  • Equipment: Quotation has been cancelled due to no-responsive firms.
  • Hanger: NTP issued for 04 Hangar (Sahastradhara, Gaucha, Naini-Saini, Chinyalisuar). Work started at Sahastradhara. Work to be started at 03 Hangars.

              

 

·         HPC sanctioned 92 Packages consisting of 110 roads of length 1968 Km amounting to INR 861.78 Cr.