Identified SubProjectSanctioned/in progressClosed

Narayanbagar-Kaub Motor Road (UID=1259)

Category: UDRP Road Reconstruction Works
Status: Sanctioned/in progress Cost (in lakhs): Rs. 535.97 Expenditure (in lakhs): Rs. 407.97
Physical Progress(%): 95.25 Photo Gallery: Show Gallery Work Code: 1259 District: Chamoli

Description:

Work is in progress.
URL:
Remarks: Civil work contract is in place and work is in progress. Contractor Name: Universal Associates ,Contract Start Date: 11-Jun-2015

Report:
Only registered users can comment. Please login.
kml link subproject ---****--- kml link realtime pics(if any)