Aso Bedapakhar Okhaldhar MR (UID=1141)

Category: UDRP Road Reconstruction Works
Status: Sanctioned/in progress Cost (in lakhs): Rs. 448.92 Expenditure (in lakhs): Rs. 342.08
Physical Progress(%): 83.72 Photo Gallery: Show Gallery Work Code: 1141 District: Bageshwar

Description:

Work is in progress.
URL:
Remarks: Civil work contract is in place and work is in progress. Contractor Name: Woodhill Infrastructure Ltd ,Contract Start Date: 01-Oct-2015