Road Selection upto 3 July 2014

User avatar er_manojbisht
Site Admin
Posts: 9
Joined: Tue Jun 24, 2014 12:33 pm
Office PIU: PIU roads and bridgesl UDRP

Road Selection upto 3 July 2014

Postby er_manojbisht » Thu Jun 26, 2014 11:56 am

Dear SE (World Bank , ADB)
please provide us the priority list of roads to be taken for World bank and ADB funded project
on the basis of following recommended line
1-Traffic in road
2-Damage extent due to mansoon damage
3-Hill area should be preferred
4-Photography needed and selection procedure should be supported by photography
5-Discussion / consent of DM and MLA
6-Resurfacing specification (BM/SDBC/PC) should be based upon traffic & service level of roads

road should be prioritized in 2 ranks 1 & 2.
1 means highly prioritized road.
target of roads to be given by each SE
1-ADB SE : 150 crore
2-WB SE : 200 crore
Er Manoj Bisht